Line 20: | Line 20: | ||
=== Mechanical === | === Mechanical === | ||
+ | |||
+ | * Photos of the NPS support structure (March 2022) | ||
+ | ::* Pic1, Pic2, Pic3 | ||
* [https://wiki.jlab.org/cuawiki/images/4/45/NPS_Status_FEB_2022psm.pptx Status February 2022 and SAD workplan] | * [https://wiki.jlab.org/cuawiki/images/4/45/NPS_Status_FEB_2022psm.pptx Status February 2022 and SAD workplan] |
Revision as of 13:24, 17 March 2022
Task List 2022
- Link to the Google Doc
Pre-assembly
- Reflector pre-shaping procedure and material
- Crystal Wrapping Procedure Link
Assembly
Mechanical
- Photos of the NPS support structure (March 2022)
- Pic1, Pic2, Pic3
Magnet
Crystals
- Overview of crystal properties
- spreadsheet from CRYTUR (January 2022) (dimensions, transmittance, light yield, radiation hardness)
DAQ/Electronics/Analyzer
- Meetings every 2 weeks. First meeting on Thursday 10 March at 9:00AM ET
- GitHub link (contact Brad, Carlos Y., or Steve W. for access)