# <b> To establish good beam conditions first send beam to the tagger dump (ask MCC to turn ON the tagger).</b> | # <b> To establish good beam conditions first send beam to the tagger dump (ask MCC to turn ON the tagger).</b> | ||
− | ## Check the beam position on the tagger viewer, it should be approximately in the center of the | + | ## Check the beam position on the tagger viewer, it should be approximately in the center of the screen |
− | ## Check profile using 2C21 and tagger harp scans, and compare the positions and widths previous scans ([https://logbooks.jlab.org/entry/3337615],[https://logbooks.jlab.org/entry/3337612]). Positions on both harps should be with +/- 1mm, widths on 2C21 shoud be ~0.05 within 0.05 mm, and on the tagger harp ~0.35mm within 0.1mm. | + | ## Check profile using 2C21 and tagger harp scans, and compare the positions and widths with previous scans ([https://logbooks.jlab.org/entry/3337615],[https://logbooks.jlab.org/entry/3337612]). Positions on both harps should be with +/- 1mm, widths on 2C21 shoud be ~0.05 within 0.05 mm, and on the tagger harp ~0.35mm within 0.1mm. |
− | + | ## Halo counters TAG-L/T/T2 should be ~10Hz/nA [https://logbooks.jlab.org/entry/3338763], | |
− | ## Halo counters TAG-L/T/T2 should be ~10Hz/nA [https://logbooks.jlab.org/entry/ | ||
# <b> While MCC degausses the tagger magnet, turn the chicane ON</b> | # <b> While MCC degausses the tagger magnet, turn the chicane ON</b> | ||
#* Strictly follow the procedure in the beam line manual! | #* Strictly follow the procedure in the beam line manual! | ||
Line 169: | Line 168: | ||
#* Check SVT is out (position 0 mm) | #* Check SVT is out (position 0 mm) | ||
# <b> Send beam to the Faraday cup</b> | # <b> Send beam to the Faraday cup</b> | ||
− | #* Ask MCC to establish | + | #* Ask MCC to establish ~25 nA beam with <font color=red>HPS</font> orbit locks on (We need HallBHPSOrb not HallBOrb configuration) |
#* Tune beam profile with 2H02A harp scan to be wide in X-direction and narrow in Y (see ref [https://logbooks.jlab.org/entry/3337720]) | #* Tune beam profile with 2H02A harp scan to be wide in X-direction and narrow in Y (see ref [https://logbooks.jlab.org/entry/3337720]) | ||
#* Check the beam spot on chromax viewer | #* Check the beam spot on chromax viewer | ||
#* The halo counter rates before HPS must be low: | #* The halo counter rates before HPS must be low: | ||
#*# UPS-L and UPS-R few Hz/nA, | #*# UPS-L and UPS-R few Hz/nA, | ||
− | #*# The tagger counters and downstream counters should count | + | #*# The tagger counters should count <Hz/na and downstream counters should count ~Hz/nA |
#*# The halo counter rates on HPS, HPS-L/R/T/SC, depends on the collimator and HPS chicane settings, but should not be more than 100 Hz/nA [https://logbooks.jlab.org/entry/3328991] | #*# The halo counter rates on HPS, HPS-L/R/T/SC, depends on the collimator and HPS chicane settings, but should not be more than 100 Hz/nA [https://logbooks.jlab.org/entry/3328991] | ||
− | #* Positions on BPMs must be close to what they were before [https://logbooks.jlab.org/entry/ | + | #* Positions on BPMs must be close to what they were before [https://logbooks.jlab.org/entry/3337725] |
− | |||
#* Insert the 4um W target without turning off the beam. | #* Insert the 4um W target without turning off the beam. | ||
#<b>Before accepting beam, make sure all the previous conditions are met. Always read previous log entries, compare settings of BPMs and correctors with previous settings using scaler_hps GUI. </b> | #<b>Before accepting beam, make sure all the previous conditions are met. Always read previous log entries, compare settings of BPMs and correctors with previous settings using scaler_hps GUI. </b> |
Revision as of 15:08, 5 May 2015
[edit]
First rule of HPS: Document all your work in the logbook!
Important Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingHPS Run Spreadsheet |
Procedures
|
Manuals |
JLab Logbooks
|
RC: Takashi Maruyama
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Stepan Stepanyan
Run Plan for May 2 - 8, 2015:During week days, Mon-Thursday, there will be no Day shifts due to work in the hall. We will be running with 1.05GeV beam. This beam needs to be carefully restored, first to the tagger dump, then to the alcove and Faraday cup screen. See detailed instructions in the right pannel. Short term schedule:
Miscellaneous Notes:
|
General Instructions:Every Shift:
Every Run:
Setting up chicane for E=1.056 GeV
SVT Instructions:
ECAL Instructions:
Acceptable Beam Conditions:
|
|
|
|
|
|
|
|
Webcams: |