Line 185: | Line 185: | ||
#* Check the beam position on the tagger viewer, it should be approximately in the center of the screen | #* Check the beam position on the tagger viewer, it should be approximately in the center of the screen | ||
#* Follow instructions under "Procedures" on the documentation tab for "Beamline"[https://wiki.jlab.org/hps-run/images/e/e6/HPS_beamline_comm.pdf]. To tune the beam on tagger dump and perform harp scans beam current should be <10 nA. | #* Follow instructions under "Procedures" on the documentation tab for "Beamline"[https://wiki.jlab.org/hps-run/images/e/e6/HPS_beamline_comm.pdf]. To tune the beam on tagger dump and perform harp scans beam current should be <10 nA. | ||
− | #* Check profile using 2C21 and tagger harp scans, and compare the positions and widths with previous scans ([https://logbooks.jlab.org/entry/ | + | #* Check profile using 2C21 and tagger harp scans, and compare the positions and widths with previous scans ([https://logbooks.jlab.org/entry/3689157],[https://logbooks.jlab.org/entry/3689156]) |
#** Positions on both harps should be within 1mm | #** Positions on both harps should be within 1mm | ||
#** Width on 2C21 should be <~0.1+/-0.05 mm | #** Width on 2C21 should be <~0.1+/-0.05 mm | ||
Line 199: | Line 199: | ||
#* If any uncertainty, page the experts | #* If any uncertainty, page the experts | ||
#* The first time sending a beam to the Faraday cup after the hall is closed, page the SVT expert. | #* The first time sending a beam to the Faraday cup after the hall is closed, page the SVT expert. | ||
− | #* Pay attention into following corrector values: 2C22H, 2C23V, 2H00H, 2H00V, Compare them to ones that are | + | #* Pay attention into following corrector values: 2C22H, 2C23V, 2H00H, 2H00V, Compare them to ones that are in [https://logbooks.jlab.org/entry/3689166]. Make sure their values don't differ more than 100%. If there is such difference, tell MCC about this. |
# ''' Send beam to the Faraday cup ''' | # ''' Send beam to the Faraday cup ''' | ||
− | #* If the beam optics is correct, then you should immediately see the beam spot on the Downstream Viewer | + | #* If the beam optics is correct, then you should immediately see the beam spot on the Downstream Viewer and on 2H00 and 2H02 BPMS. |
#* If you don't see it immediately, and rates on halo counters are more than 100 Khz, then ask MCC, to change to pulsed (tune mode) beam, and ask to put corrector values. At this point don't accept any CW beam, until beam spot is visible on Downstream Viewer. | #* If you don't see it immediately, and rates on halo counters are more than 100 Khz, then ask MCC, to change to pulsed (tune mode) beam, and ask to put corrector values. At this point don't accept any CW beam, until beam spot is visible on Downstream Viewer. | ||
#* If MCC operator is not able to tune the beam more than 30 minutes, then please notify RC | #* If MCC operator is not able to tune the beam more than 30 minutes, then please notify RC | ||
Line 212: | Line 212: | ||
#*# UPS-L and UPS-R few Hz/nA, | #*# UPS-L and UPS-R few Hz/nA, | ||
#*# The tagger counters should count less than Hz/nA and downstream counters should count ~Hz/nA | #*# The tagger counters should count less than Hz/nA and downstream counters should count ~Hz/nA | ||
− | #*# The halo counter rates on HPS, HPS-L/R/T/SC, depends on the collimator and HPS chicane settings, but should not be more than 100 Hz/nA [https://logbooks.jlab.org/entry/ | + | #*# The halo counter rates on HPS, HPS-L/R/T/SC, depends on the collimator and HPS chicane settings, but should not be more than 100 Hz/nA [https://logbooks.jlab.org/entry/3689166] |
− | #* Positions on BPMs must be close to what they were before [https://logbooks.jlab.org/entry/ | + | #* Positions on BPMs must be close to what they were before [https://logbooks.jlab.org/entry/3689166] |
+ | #* Check the beam profile using 2H01A and 2H02A harps and compare the positions and widths with previous scans ([https://logbooks.jlab.org/entry/3689164],[https://logbooks.jlab.org/entry/3689165]) | ||
#* Once all the above is achieved, turn ECAL and Hodoscope HV '''ON''' to monitor and log ECal rates | #* Once all the above is achieved, turn ECAL and Hodoscope HV '''ON''' to monitor and log ECal rates | ||
#* Insert the 4um W target without turning off the beam. | #* Insert the 4um W target without turning off the beam. |
Revision as of 03:58, 17 June 2019
[edit]
Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingRun Spreadsheet 2019,2016, 2015HPS Upgrade ERR |
Procedures
|
Manuals |
JLab Logbooks
|
HPS 2019 run, June X to August Y'
Beam energy 4.5 GeV
Important: Document all your work in the logbook!
Bluejeans for Run Meetings on DAY and DAY at 2pm
RC: Stepan Stepanyan
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Valery Kubarovsky
- (757) 876-1789
- 9 876-1789 from Counting Room
* !! Chicane magnets can be energized only when the hall is in Beam Permit, [1]. Chicane magnets must be off if the hall is in Restricted or in Controlled access.
* The vacuum gauge used in SVT interlock (2H03) is broken. Watch the gauge 2H02, in case of a vacuum event valves will close and the beam will be shut-off. If the event is at 2H02 (loss of vacuum near HPS chamber) call SVT expert immediately and follow his/her instruction.
Run Plan June 15 - 17, 2019
Important Notes:
|
General InstructionsDAQ RECOVERYIf DAQ crashed/broken:
Establishing Physics Quality Beam for HPS:
Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.
Setting up the FSD threshold
hpsrun@clonpc11> /home/hpsrun/scripts/FSD/Calc_FSD_Threshold.exe
|
Every Shift:
|
Every Run:
|
---|
RC daily meetings at 2 pm in the counting-house 2nd-floor conference room.
BlueJeans Info:
URL: https://bluejeans.com/794825703
Meeting ID: 794825703
|
|
|
Webcams:
|
Accelerator: |
Slow Controls:
|
Online & Offline: |
System/Person | Pager/Phone Number |
---|---|
Run Coordinator | (757) 575-7540 (cell) |
Physics Div. Liaison | (757) 876-1789 (cell) |
MCC-OPS | 7048 |
Crew Chief | 7045 |
Crew Chief | 9-879-3367 (cell) |
Program Deputy | 9-876-7997 (cell) |
Gate House Guard | 5822 |
DAQ/Online | (757) 869-2188 (cell) |
SVT | (757) 310-7198 (cell) |
ECAL | (757) 810-1489 (cell) |
Slow Controls | (757) 748-6922 (cell) |
Beamline | (757) 303-3996 (cell) |
Engineering | (757) 748-5048 |
Hall-B Floor | 5165 |
Hall-B Space Frame | 5170, 5171 |
Hall-B Forward Carriage | 5371 |
Hall-B Counting Room | 5126, 5244, 5246, 5247 |
Hall-B Gas Shed | 7115 |