Difference between revisions of "The HPS Run Wiki"

From hps run
Jump to navigation Jump to search
Line 252: Line 252:
 
<b> Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.</b>
 
<b> Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.</b>
 
#* Ask MCC to establish 30 nA beam with <font color=red>HPS</font> orbit locks on (We need '''HallBHPSOrb''' not '''HallBOrb''' configuration). <b>For orbit lock positions on <font color=red>2H00(X=0.3,Y=-1.) and on 2H02(X=-2.4,Y=-0.9). Use the 2.82 mm SVT collimator. (positions changed 6/25/19 by mg)</font></b>.  
 
#* Ask MCC to establish 30 nA beam with <font color=red>HPS</font> orbit locks on (We need '''HallBHPSOrb''' not '''HallBOrb''' configuration). <b>For orbit lock positions on <font color=red>2H00(X=0.3,Y=-1.) and on 2H02(X=-2.4,Y=-0.9). Use the 2.82 mm SVT collimator. (positions changed 6/25/19 by mg)</font></b>.  
#* Tune beam profile at HPS using measured widths on 2H01A and 2H02A harps. The required beam profile at 2H02A harp is: X-width <~0.1 mm, Y-width <~ 0.05 mm. Beam profile using 2H01A and 2H02A harps with previous scans ([https://logbooks.jlab.org/entry/3696650],[https://logbooks.jlab.org/entry/3903891) to compare.
+
#* Tune beam profile at HPS using measured widths on 2H01A and 2H02A harps. The required beam profile at 2H02A harp is: X-width <~0.1 mm, Y-width <~ 0.05 mm. Beam profile using 2H01A and 2H02A harps with previous scans ([https://logbooks.jlab.org/entry/3696650],[https://logbooks.jlab.org/entry/3903891]) to compare.
 
#* Check and log the beam spot on chromax viewer
 
#* Check and log the beam spot on chromax viewer
 
#* The halo counter rates before HPS must be very low:  
 
#* The halo counter rates before HPS must be very low:  

Revision as of 13:10, 11 September 2021


[edit]

HPS (E12-11-006) 2021 run, August - October'
Beam energy 3.74 GeV
Important: Document all your work in the logbook!
Bluejeans for Run Meetings on DAY and DAY at 3 pm

RC: Maurik Holtrop

  • (757) 575-7540
  • 9 575 7540 from Counting Room
  • Personal cell: +1 (207) 535-7037

PDL: Valery Kubarovsky

  • (757) 876-1789
  • 9 876-1789 from Counting Room

Important instructions

* Turn OFF beam before target move!

* No access to the alcove if the chicane magnet beacon is ON.

Chicane magnets must be OFF if the hall is in Controlled access and access to the alcove is needed or when the hall is in Restricted access. If Chicane magnets are OFF, they can be energized only when the hall is in Power or Beam Permit, [1].

* TURN OFF the chicane magnet if beam is not available due to a thunderstorm. Loss off power would seriously damage detectors.

* Fill out BTA hourly. Click "Load from EPICS" to fill the left side, then make sure numbers are correct. If needed edit the entry.

NO ABUs or BANU if beam tune is in progress, make it all BNA with ER 100%. At the end of the shift save BTA to the logbook!

* Please close any GUI that is not being used, e.g. close harp scanner after harp scan is done, close chicane, after chicane is ON, etc.

* For orbit lock positions on 2H00(X=0.3,Y=-1.) and on 2H02(X=-2.4,Y=-0.9). Use the 2.82 mm SVT collimator

Before 9/9 this was: 2H00(X=0.3,Y=-1.) and on 2H02(X=-2.4,Y=-1.). Use the 2.82 mm SVT collimator

Run Plan September 10 - 11, 2021

  • Take production data: 120 nA beam on the 20 um W target, PROD77 configuration, production trigger (see white board)
  • Special runs:
    • Short Moller run, ~ 1 hour with Moller trigger only. Moller trigger prescale changed to give 24 kHz trigger rate for 60 nA of beam.
    • Random Trigger run, ~ 2 hour run at full luminosity ( 120 nA), with Faraday Cup and Pulser trigger only, changed to give 24 kHz trigger rate.
  • Monday around 6am (maybe a bit earlier) the beam will be taken away to setup Hall-D. This is very likely to go well into swing shift and may spill over into the owl shift.

Hall Access Items:

  • Add one more channel of halo counters to beam modulation scheme - Stepan/Nathan (1 hour)

Every Shift:

  1. Follow the run plan as outlined by RC
  2. With any issue contact On-Call Experts or RC
  3. Monitor carefully the SVT bias current (see below for details)
  4. If any concern about beam stability, ask MCC if orbit locks are on (they should be ON).
  5. Keep shift summary up to date in HBLOG. Record all that happens.
    • Document any beam condition change and send scaler GUIs to HBLOG
    • Fill out BTA hourly. Click "Load from EPICS" to automatically fill the left side then make sure numbers are correct. If needed edit the entry. Note: in the "Sift information" tab choose experiment E12-11-006. . At the end of the shift send BTA to teh logbook.
    • Fill and submit the shift checklist in the logbook

Every Run:

  1. After "Go": Check SVT Occupancy
  2. Update the Run Spreadsheet
  3. Log screenshots of:
    • main scaler_hps display
    • ECAL FADC rate gui
    • Trigger rate gui
    • SVT and HODOSCOPE and ECAL Monitoring pdfs
  4. Please watch Hybrid sync GUI for correct status (currently three red lights) and the L0-3 and L4-6 occupancy plots for any empty plots beyond the expected three.

SVT Bias Currents:

Shifters must pay attention to the L0 bias currents. This is on both the SVT motor GUI and the main bias GUI. The bias currents will slowly creep up over the course of a run. When the bias current is between 15-20 uA for either L0 sensor, do the following:

  1. Stop the run.
  2. Take the beam away, turn off SVT bias voltages, and wait 10 min.
  3. Turn the bias voltages back on.
  4. Check that the L0 bias currents have gone back down to ~4 uA
  5. Bring back the beam and start a new run.

Do not let the bias current exceed 20 uA. It takes about 4-5 hours for the bias currents to creep up to those values. Call SVT expert if unsure.

Harp Scan Procedure:

  1. During harp scans, SVT must be retracted (motors/SVT Positioners). HVs on SVT, ECal and Hodoscope should be OFF.
  2. Halo counter FSDs (Downstream, HPS Up and HPS Down) are masked, Beam current 100 nA, Orbit locks running.
  3. Perform the HARP scan, log the results.
  4. If the beam looks different, you should call beam-line on-call that will advise on the next steps.
  5. If the beam looks different, perform SVT wire scan, the target needs to be retracted as well for this one.

Important Notes:

  1. When re-establishing beam to Hall B after a >1h long downtime follow "General Guidelines" on the right and the Beamline Procedures and Manual on the shift documentation page. Do not hesitate to call the beamline expert.
  2. Do not run more than 60 minutes above 30 nA without the beam blocker in front of Faraday cup. Put beam blocker in for long running at high currents.
  3. For SVT Operations:
    • From the time beam first comes into the hall until it is being delivered to the Faraday cup with orbit locks on for a known good trajectory, the SVT should be completely off. This is especially important during tuning to the tagger dump, when mis-steering of the beam can result in very high hard neutron backgrounds.
    • Once stable beam is being delivered to the Faraday cup with orbit locks on for a known good trajectory, and the SVT collimator is in position, the FEBs and hybrids can be powered and operated, but the HV bias for the sensors must remain off.
    • In order to turn on the HV, the FSD system must be functioning so a beam excursion that hits the collimator will quickly trip off the beam.

General Instructions

Establishing Physics Quality Beam for HPS:

  1. Make sure SVT is retracted and detectors, SVT, Hodoscope and ECAL are OFF.
  2. If the beam was off for 4 hours or more or in case of troublesome beam tuning, send a beam to the tagger dump:
    • Check that beam type is set to "Photon" (HPS_EPICS->Beam->BTA).
    • Position "Blank" on the beam for the Hall-B collimator
    • Ask MCC to turn ON the tagger magnet and then deliver <10 nA beam to the tagger dump.
    • Check the beam position on the tagger viewer, it should be approximately in the center of the screen
    • Follow instructions under "Procedures" on the documentation tab for "Beamline"[2]. To tune the beam on tagger dump and perform harp scans beam current should be <10 nA.
    • Check profile using 2C21 and tagger (2C24) harp scans and compare the positions and widths with previous scans ([3],[4])
      • Positions on both harps should be within 1mm
      • Width on 2C21 should be <~0.2+/-0.05 mm
      • Width on tagger harp (2C24) <~0.5 +/- 0.1mm
    • Background levels on harp scans are comparable to those of previous scans.
  3. Before sending a beam to the Faraday cup
    • If HPS chicane must be ON, make sure that chicane GUI says "Chicane Ready"
    • Set Hall-B Collimator to 20 mm.
    • Check that SVT protection collimator is ON THE BEAM (2.82 mm). If the beam was off for more than 4 hours or the configuration has changed, start with 8 mm
    • HPS target is OUT and Hodoscope and ECAL HVs are OFF
    • SVT is OUT (positions -1.8987 mm for top and -2,2025 for bottom on the main HPS scaler GUI) and bias HV is off (all red/green indicators RED in SVT bias GUI)
    • If any uncertainty, page the experts
    • Pay attention to the following corrector values: 2C22H, 2C23V, 2H00H, 2H00V, Compare them to ones that are in [5]. Make sure their values don't differ more than 100%. If there is such a difference, tell MCC about this.
  4. Send beam to the Faraday cup
    • If the beam optics is correct, then you should immediately see the beam spot on the Downstream Viewer and on the 2H00 and 2H02 BPMS.
    • If you don't see it immediately, and rates on halo counters are more than 100 Khz, then ask MCC, to change to pulsed (tune mode) beam, and ask to restore corrector values. At this point don't accept any CW beam, until the beam spot is visible on Downstream Viewer.
    • If the MCC operator is not able to tune the beam for more than 30 minutes, then notify RC!
    • Follow the instructions under "Procedures" on the documentation tab for "Beamline"[6] to establish beam to the electron dump.

Note: in order to have reliable readings on two important for HPS BPMs, 2H00 and 2H02, beam current should be >30 nA.

    • Ask MCC to establish 30 nA beam with HPS orbit locks on (We need HallBHPSOrb not HallBOrb configuration). For orbit lock positions on 2H00(X=0.3,Y=-1.) and on 2H02(X=-2.4,Y=-0.9). Use the 2.82 mm SVT collimator. (positions changed 6/25/19 by mg).
    • Tune beam profile at HPS using measured widths on 2H01A and 2H02A harps. The required beam profile at 2H02A harp is: X-width <~0.1 mm, Y-width <~ 0.05 mm. Beam profile using 2H01A and 2H02A harps with previous scans ([7],[8]) to compare.
    • Check and log the beam spot on chromax viewer
    • The halo counter rates before HPS must be very low:
      1. Upstream Left and Right, and the tagger counters few 10's of Hz,
      2. Downstream counters should count <Hz/nA
      3. The halo counter rates on HPS, HPS-L/R/T/SC, depends on the collimator and HPS chicane settings, but should not be more than 50 Hz/nA [9]
    • Positions on BPMs must be close to what they were before [10]
    • When everything is stable, perform SVT wire scan and compare with the nominal [11]
    • Once all the above is achieved, turn ECAL and Hodoscope HV ON to monitor and log ECal rates
    • Insert the 20 um W target (turn beam off first).
  1. Before accepting the beam, make sure all the previous conditions are met. Always read previous log entries, compare settings of BPMs and correctors with previous settings using scaler_hps GUI.




RC daily meetings at 3 pm in the counting-house 2nd-floor conference room.

BlueJeans Info:

URL: https://bluejeans.com/759437905/8110

Meeting ID: 759437905

Status of the run

Run Coordinator
08/23 - 09/01 Stepan Stepanyan
09/01 - 09/08
09/08 - 09/15 Maurik Holtrop
09/15 - 09/22
09/22 - 09/29 Tim Nelson
09/29 - 10/06 Rafayel Paremuzyan
10/06 - 10/13
10/13 - 10/20 Cameron Bravo
Physics Division Liaison
Valery Kubarovsky
Beamline
Eugene Pasyuk
SlowControls
Nathan Baltzell
ECAL/HODOSCOPE
Nathan Baltzell
DAQ
Sergey Boyarinov
SVT
08/23 - 09/02 Tim Nelson
09/02 - Cameron Bravo
- Omar Moreno
- Matt Solt
- Vitaliy Fadeyev
- Matt Solt


System/Person Pager/Phone Number
Run Coordinator (757) 575-7540 (cell)
Physics Div. Liaison (757) 876-1789 (cell)
MCC-OPS 7048
Crew Chief 7045
Crew Chief 9-879-3367 (cell)
Program Deputy 9-876-7997 (cell)
Gate House Guard 5822
DAQ/Online (757) 869-2188 (cell)
SVT (757) 329-4844 (cell)
ECAL/Hodo (757) 310-7198 (cell)
Slow Controls (757) 748-6922 (cell)
Beamline (757) 303-3996 (cell)
Engineering (757) 748-5048
Hall-B Floor 5165
Hall-B Space Frame 5170, 5171
Hall-B Forward Carriage 5371
Hall-B Counting Room 5244(Shift1), 5245(Shift2)
Hall-B Counting Room 5247(Expert), 5502(Target)
Hall-B Counting Room 5246(RC1), 5126(RC2)
Hall-B Gas Shed 7115


Overview

  • Bluejeans for 24-7 communication with counting house: https://bluejeans.com/950041022
  • Remote VNC connection instructions: https://logbooks.jlab.org/entry/3880107
    • All necessary applications should be avaible from the desktop menu (left/right click on the desktop)
  • EPICS GUIs should be accessed ONLY via the desktop menu or by running hps_epics_remote.

Tasks

Shift Worker Backup Table

To add your name, edit this wiki page or send email to Maurik or Nathan.

Worker Shift Backup
Date Day Swing Owl
Fri, Sep 10 Alessandra Filippi Natasa Dashyan -
Sat, Sep 11 Raffaella De Vita Valeria Sipala Domenico D'Urso
Sun, Sep 12 Andrea Celentano Valeria Sipala Domenico D'Urso
Mon, Sep 13 Luca Marsicano Valeria Sipala Domenico D'Urso
Tue, Sep 14 Luca Marsicano Valeria Sipala Domenico D'Urso
Wed, Sep 15 Raffaella De Vita - Valeria Sipala
Thu, Sep 16 Luca Marsicano - Valeria Sipala
Fri, Sep 17 Andrea Celentano - Valeria Sipala
Sat, Sep 18 Andrea Celentano - Valeria Sipala
Sun, Sep 19 - Annalisa D'Angelo -
Mon, Sep 20 - Alessandra Filippi -
Tue, Sep 21 - Alessandra Filippi -
Wed, Sep 22 - Alessandra Filippi -
Thu, Sep 23 - Andrea Celentano Nunzio Randazzo
Fri, Sep 24 - Raffaella De Vita Nunzio Randazzo
Sat, Sep 25 - Raffaella De Vita Nunzio Randazzo
Sun, Sep 26 - Luca Marsicano Nunzio Randazzo
Mon, Sep 27 Gabriele Simi - -
Tue, Sep 28 Gabriele Simi - -
Wed, Sep 29 Gabriele Simi - -
Thu, Sep 30 Gabriele Simi - -
Fri, Oct 1 - - Marzio de Napoli
Sat, Oct 2 - - Marzio de Napoli
Sun, Oct 3 - - Marzio de Napoli
Mon, Oct 4 - - Marzio de Napoli
Tue, Oct 5 - - Annalisa D'Angelo
Wed, Oct 6 - - Annalisa D'Angelo
Thu, Oct 7 - - Annalisa D'Angelo
Fri, Oct 8 - - Annalisa D'Angelo
Sat, Oct 9 Alessandra Filippi Gabriele Simi Luca Marsicano
Sun, Oct 10 Annalisa D'Angelo Gabriele Simi Luca Marsicano
Mon, Oct 11 Annalisa D'Angelo Gabriele Simi Andrea Celentano
Tue, Oct 12 Annalisa D'Angelo Gabriele Simi Andrea Celentano
Wed, Oct 13 - Luca Marsicano Domenico D'Urso
Thu, Oct 14 - Andrea Celentano Domenico D'Urso
Fri, Oct 15 - Mariangela Bondì Domenico D'Urso
Sat, Oct 16 - Mariangela Bondì Domenico D'Urso
Backup shifter contact info
Name Email Cell phone
Annalisa D'Angelo annalisa.dangelo@roma2.infn.it +393473634490/(call

through WhatsApp if not reachable)

Alessandra Filippe filippi@to.infn.it +39 328 9411758
Andrea Celentano andrea.celentano@ge.infn.it ‭+39 340 9831283‬
Domenico D'Urso ddurso@uniss.it +39 349 3630 242
Gabriele Simi gabriele.simi@pd.infn.it +39 320 748 3385
Hakob Voskania voskania@jlab.org +37495909998
Luca Marsicano luca.marsicano@ge.infn.it +39 333 9893725‬
Mariangela Bondì mariangela.bondi@ge.infn.it +39 ‭327 1895733‬
Marzio de Napoli marzio.denapoli@ct.infn.it +39-3498834468
Maurik Holtrop holtrop@jlab.org +1-603-868-8088
Natasa Dashyan natasha@jlab.org +37477538360
Nathan Baltzell baltzell@jlab.org +1 757 748 6922
Nunzio Randazzo nunzio.randazzo@ct.infn.it +39-3472591331
Raffaella De Vita Raffaella.Devita@ge.infn.it +39 340 8110156
Raphaël Dupré raphael.dupre@ijclab.in2p3.fr +33 670 977 761
Silvia Niccolai silvia@jlab.org +33 624 81 67 78
Valeria Sipala vsipala@uniss.it +39 339 339 57 04


Svtpic.png

Ecalpic.png