Line 153: | Line 153: | ||
#* Check SVT is out (position 0 mm) | #* Check SVT is out (position 0 mm) | ||
# <b> Send beam to the Faraday cup</b> | # <b> Send beam to the Faraday cup</b> | ||
+ | #* Ask MCC to establish HPS orbit locks | ||
#* Tune beam profile with 2H02A harp scan to be wide in X-direction and narrow in Y (see ref [https://logbooks.jlab.org/entry/3334783]) | #* Tune beam profile with 2H02A harp scan to be wide in X-direction and narrow in Y (see ref [https://logbooks.jlab.org/entry/3334783]) | ||
#* Check the beam spot on chromax viewer | #* Check the beam spot on chromax viewer | ||
Line 161: | Line 162: | ||
#* Positions on BPMs must be close to what they were before [https://logbooks.jlab.org/entry/3334787] | #* Positions on BPMs must be close to what they were before [https://logbooks.jlab.org/entry/3334787] | ||
#* Contact SVT expert to do SVT Wire Scan | #* Contact SVT expert to do SVT Wire Scan | ||
− | |||
#* Ask beam to be turned OFF to insert the 4um W target | #* Ask beam to be turned OFF to insert the 4um W target | ||
#<b>Before accepting beam, make sure all the previous conditions are met. Always read previous log entries, compare settings of BPMs and correctors with previous settings using scaler_hps GUI. </b> | #<b>Before accepting beam, make sure all the previous conditions are met. Always read previous log entries, compare settings of BPMs and correctors with previous settings using scaler_hps GUI. </b> |
Revision as of 16:54, 25 April 2015
[edit]
First rule of HPS: Document all your work in the logbook!
Important Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingHPS Run Spreadsheet |
Procedures
|
Manuals |
JLab Logbooks
|
RC: Raphael Dupre
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Stepan Stepanyan
Run Plan for April 23-30, 2015:During week days, Mon-Thursday, there will be no Day shifts due to work in the hall. We will be running with 1.05GeV beam. This beam needs to be carefully restored, first to the tagger dump, then to the alcove and Faraday cup screen. See detailed instructions in the right pannel. Short term schedule:
Miscellaneous Notes:
|
General Instructions:Every Shift:
SVT Instructions:
Acceptable Beam Conditions:
|
Long Term Schedule Proposal PowerPoint
|
|
|
|
|
|
|
Webcams: |
Trigger: |
Accelerator: Slow Controls:
|
Online & Offline: |