Difference between revisions of "The HPS Run Wiki"
Jump to navigation
Jump to search
Line 154: | Line 154: | ||
# <b> To establish good beam conditions first send beam to the tagger dump (ask MCC to turn ON the tagger).</b> | # <b> To establish good beam conditions first send beam to the tagger dump (ask MCC to turn ON the tagger).</b> | ||
## Check position, it should corresponds to previous good settings [https://logbooks.jlab.org/entry/3334787] | ## Check position, it should corresponds to previous good settings [https://logbooks.jlab.org/entry/3334787] | ||
− | ## Check profile using 2C21 and tagger harp scans, it should correspond to previous settings ([https://logbooks.jlab.org/entry/ | + | ## Check profile using 2C21 and tagger harp scans, it should correspond to previous settings ([https://logbooks.jlab.org/entry/3337615],[https://logbooks.jlab.org/entry/3337612]) |
## Beam can be accepted at this level if it is within 20% of previous standards | ## Beam can be accepted at this level if it is within 20% of previous standards | ||
## Halo counters TAG-L/T/T2 should be ~10Hz/nA [https://logbooks.jlab.org/entry/3326723], | ## Halo counters TAG-L/T/T2 should be ~10Hz/nA [https://logbooks.jlab.org/entry/3326723], | ||
Line 165: | Line 165: | ||
# <b> Send beam to the Faraday cup</b> | # <b> Send beam to the Faraday cup</b> | ||
#* Ask MCC to establish 30 nA beam with <font color=red>HPS</font> orbit locks on (We need HallBHPSOrb not HallBOrb configuration) | #* Ask MCC to establish 30 nA beam with <font color=red>HPS</font> orbit locks on (We need HallBHPSOrb not HallBOrb configuration) | ||
− | #* Tune beam profile with 2H02A harp scan to be wide in X-direction and narrow in Y (see ref [https://logbooks.jlab.org/entry/ | + | #* Tune beam profile with 2H02A harp scan to be wide in X-direction and narrow in Y (see ref [https://logbooks.jlab.org/entry/3337731]) |
#* Check the beam spot on chromax viewer | #* Check the beam spot on chromax viewer | ||
#* The halo counter rates before HPS must be low: | #* The halo counter rates before HPS must be low: |
Revision as of 13:06, 2 May 2015
[edit]
First rule of HPS: Document all your work in the logbook!
Important Phone NumbersShift ScheduleShift-Taker's ChecklistHot CheckoutBeam Time AccountingHPS Run Spreadsheet |
Procedures
|
Manuals |
JLab Logbooks
|
RC: Takashi Maruyama
- (757) 575-7540
- 9 575 7540 from Counting Room
PDL: Stepan Stepanyan
Run Plan for May 2 - 8, 2015:During week days, Mon-Thursday, there will be no Day shifts due to work in the hall. We will be running with 1.05GeV beam. This beam needs to be carefully restored, first to the tagger dump, then to the alcove and Faraday cup screen. See detailed instructions in the right pannel. Short term schedule:
Miscellaneous Notes:
|
General Instructions:Every Shift:
Setting up chicane for E=1.056 GeV
SVT Instructions:
ECAL Instructions:
Acceptable Beam Conditions:
|
|
|
|
|
|
|
|
Webcams: |
Trigger: |
Accelerator: Slow Controls:
|
Online & Offline: |