== Run Plan September 29 - October 1, 2021 ==
 
== Run Plan September 29 - October 1, 2021 ==
  
* Restor beam for production running (see procedures on the right)
+
* Restor physics quality beam for the production running (see procedures on the right)
 
* '''Take production data''':  120 nA beam on the 20 um W target, PROD77 configuration, production trigger '''hps2021_v2_3.trg'''. Each run should last about 4 hours.
 
* '''Take production data''':  120 nA beam on the 20 um W target, PROD77 configuration, production trigger '''hps2021_v2_3.trg'''. Each run should last about 4 hours.
  