== Run Plan October 1 - 5, 2021 ==
+
== Run Plan October 5 - 7, 2021 ==
  
<!-- * Restor physics quality beam for the production running (see procedures on the right) -->
+
* Restore physics quality beam for the production running, start from the tagger dump (see instructions on the right)
 
* '''Take production data taking''':  120 nA beam on the 20 um W target, PROD77 configuration, production trigger '''hps2021_v2_3.trg'''. Each run should last about 4 hours.
 
* '''Take production data taking''':  120 nA beam on the 20 um W target, PROD77 configuration, production trigger '''hps2021_v2_3.trg'''. Each run should last about 4 hours.
* At 8 am on Tuesday, October 5, Stop data taking, turn OFF detectors, retract SVT and get ready for 2H02 harp scans to study the effect of the prebuncher setting on the beam profile (see test plan https://opsweb.acc.jlab.org/CSUEApps/atlis/task/23350)
+
** Anytime MCC turns OFF or ON Hall-C, HPS SVT bias HV must be OFF, SVT retracted to 3 mm position
* Beam will be down and the hall will go to restricted access around 9:30 am on Tuesday, October 5, for the tour and the hall work (see below)
+
** Be aware Hall-A will come up sometime on Wednesday, October 6
* If an opportunity arises (long machine down), request controlled access to refill the SVT chiller and reset the chiller camera. When restoring the beam from the long down, contact RC to see if the prebuncher test above can be performed at the same time.
 
  
  