* '''Take production data taking''':  120 nA beam on the 20 um W target, PROD77 configuration, production trigger '''hps2021_v2_3.trg'''. Each run should last about 4 hours.
 
* '''Take production data taking''':  120 nA beam on the 20 um W target, PROD77 configuration, production trigger '''hps2021_v2_3.trg'''. Each run should last about 4 hours.
** if the beam is down for less than 40 min for reasons that will not alter the beam trajectory to Hall-B, do not end the run instead pause DAQ with:  
+
** if the beam is down for less than 40 min for reasons that will not alter the beam trajectory to Hall-B, do not end the run instead pause DAQ by running the script on <bf> clondaq7 </bf>:  
 
***<font color=red> tcpClient hps11 'tsDisableTriggerSource(0)' </font>, retract the SVT to 3 mm, leave the bias voltages ON.  
 
***<font color=red> tcpClient hps11 'tsDisableTriggerSource(0)' </font>, retract the SVT to 3 mm, leave the bias voltages ON.  
 
** After the beam is back and the halo and the detector rates look the same, bring the SVT to 0.5 mm and un-pause DAQ   
 
** After the beam is back and the halo and the detector rates look the same, bring the SVT to 0.5 mm and un-pause DAQ   
Line 167: Line 167:
 
# Keep shift summary up to date in HBLOG. Record all that happens.
 
# Keep shift summary up to date in HBLOG. Record all that happens.
 
#* Document any beam condition change and send scaler GUIs to HBLOG
 
#* Document any beam condition change and send scaler GUIs to HBLOG
#* [https://bta.acc.jlab.org Fill out BTA] hourly.  Click "Load from EPICS" to automatically fill the left side then make sure numbers are correct. If needed edit the entry. Note: in the "Sift information" tab choose experiment <font color=blue> E12-11-006. </font>. At the end of the shift send BTA to teh logbook.
+
#* [https://bta.acc.jlab.org Fill out BTA] hourly.  Click "Load from EPICS" to automatically fill the left side then make sure numbers are correct. If needed edit the entry. Note: in the "Sift information" tab choose experiment <font color=blue> E12-11-006. </font>. At the end of the shift send BTA to the logbook.
 
#* Fill and submit the [https://logbooks.jlab.org/checklists/530 shift checklist in the logbook]
 
#* Fill and submit the [https://logbooks.jlab.org/checklists/530 shift checklist in the logbook]
  