Difference between revisions of "August 30th, 2022"

From kl project
Jump to navigation Jump to search
Line 6: Line 6:
 
* On August 12th, we had a ''Tim's'' discussion for 2023 budget and what we will be ready to procure for the project [https://halldweb.jlab.org/wiki/index.php/August_12,_2022_KLONG_Phase_II_Design_Meeting].
 
* On August 12th, we had a ''Tim's'' discussion for 2023 budget and what we will be ready to procure for the project [https://halldweb.jlab.org/wiki/index.php/August_12,_2022_KLONG_Phase_II_Design_Meeting].
  
* On August 22th, we had a ''Hovanes'' CPS meeting for a development of the conseptual design of the Tiger hall with CPS [https://wiki.jlab.org/klproject/index.php/CPS_meeting_-_August_22,_2022]. CPS temperature map calculations (''Tim'') [https://wiki.jlab.org/klproject/images/2/20/CPS_steady_state_thermal_v8.pdf]. Updates on the CPS conceptual design and activation dose for the KPT (''Vitaly'') [].
+
* On August 22th, we had a ''Hovanes'' CPS meeting for a development of the conseptual design of the Tiger hall with CPS [https://wiki.jlab.org/klproject/index.php/CPS_meeting_-_August_22,_2022]. CPS temperature map calculations (''Tim'') [https://wiki.jlab.org/klproject/images/2/20/CPS_steady_state_thermal_v8.pdf]. Updates on the CPS conceptual design and activation dose for the KPT (''Vitaly'') [https://wiki.jlab.org/klproject/images/c/ca/CPS-SHIELDSTUDY-082222.pdf].
  
 
* On August 26th, ''Tanja Horn'' had a ''CPS'' meeting (main focus is CPS for Hall C)[https://wiki.jlab.org/cuawiki/index.php/Meeting_26_August_2022].
 
* On August 26th, ''Tanja Horn'' had a ''CPS'' meeting (main focus is CPS for Hall C)[https://wiki.jlab.org/cuawiki/index.php/Meeting_26_August_2022].

Revision as of 19:46, 24 August 2022

Attended: ... and Igor.


  • On August 8th, we had a Hovanes CPS meeting for a development of the conseptual design of the Tiger hall with CPS [1]. Temperature map calculations (Tim) [2] and Update on conceptual design (Vitaly) [3]. Hovanes added a document that among other things specifies the change in the magnetic field of the PDV permanent magnets that we use in Hall D after some average dose received by the magnet. It also defines the material of the permanent magnet as "Type 8 Strontium Ferrite" [4].
  • On August 12th, we had a Tim's discussion for 2023 budget and what we will be ready to procure for the project [5].
  • On August 22th, we had a Hovanes CPS meeting for a development of the conseptual design of the Tiger hall with CPS [6]. CPS temperature map calculations (Tim) [7]. Updates on the CPS conceptual design and activation dose for the KPT (Vitaly) [8].
  • On August 26th, Tanja Horn had a CPS meeting (main focus is CPS for Hall C)[9].


  • Eugene informed us that we have to have a readeness review for the KLF in January 2023. Patrizia will assign a committee and gave us a chart.


  • We have to improve KPT at [10] and merge [11] with [12] and CPS [13] documents (all is on Overleaf).


  • Moskov suggested to call for the 6th KLF Collaboration meeting this fall 2022. We have to discuss agenda.