Run Meeting: February 27th, 2018
Back to Main Page Daily_Run_Meetings
4:00PM Run Meeting, Counting house meeting room (200C)
Summary of past 24h:
- Swing: LHRS magnets brought back up around 18:30. Resumed production only with the left arm for H3. RHRS back in business around 23:30. Moved target to D2 and started data taking with both spectrometers.
- Owl: Smooth running. Target changed to He3 around 2:45 as we finished column 19/24.
- Day: RF recovery scheduled for 4 hours. Started with RF diagnostics at 8:30 sending high current to A&C for finding troublesome cavities. Target stayed in Home position throughout the RF work. Back in production mode around 12:40 as planned.
Plan: Continue production!!!