Installation and Configuration

With First Beam (2018-01-11 - 2018-01-12)

  1. Beamline
    1. Beam Centering
    2. Raster Size Calibration
    3. BPM Calibration (pedestal run, Bullseye scan)
    4. ARC Energy Measurement (parasitic only)
  2. DAQ and Trigger Checkout
  3. Detector Checkout / Optics
  4. Optics commissioning HRS Optics Run
  5. Detector Calibrations (in parallel with other activities once we have the electron data)