Difference between revisions of "Additional Installation and Commissioning"

From Tritium Experiments Group
Jump to navigation Jump to search
(Created page with "[https://wiki.jlab.org/tegwiki/index.php/2018_Srping_Run <B>Back to 2018 Spring Run Plan</B>] [https://wiki.jlab.org/tegwiki/index.php/Main_Page <B>Back to Tritium-Main</B>]")
 
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
[https://wiki.jlab.org/tegwiki/index.php/2018_Srping_Run <B>Back to 2018 Spring Run Plan</B>]
 
[https://wiki.jlab.org/tegwiki/index.php/2018_Srping_Run <B>Back to 2018 Spring Run Plan</B>]
 
[https://wiki.jlab.org/tegwiki/index.php/Main_Page <B>Back to Tritium-Main</B>]
 
[https://wiki.jlab.org/tegwiki/index.php/Main_Page <B>Back to Tritium-Main</B>]
 +
 +
=[[Installation and Configuration]]=
 +
 +
=With First Beam (2018-01-11 - 2018-01-12)=
 +
 +
<ol>
 +
 +
<li> Beamline
 +
<ol>
 +
  <li> [[Beam Centering]]
 +
  <li> [[Raster Size Calibration]]
 +
  <li> [[BPM Calibration]] (pedestal run, Bullseye scan)
 +
  <li> [[ARC Energy Measurement]] (parasitic only)
 +
</ol>
 +
 +
<li> [https://wiki.jlab.org/tegwiki/index.php/Data_Acquisition_System_and_Triggers DAQ and Trigger Checkout]
 +
 +
<li> [https://wiki.jlab.org/tegwiki/index.php/Detector_Checkout_with_single_foil,_multi_foils,_and_target_cells Detector Checkout / Optics]
 +
 +
<li> [https://wiki.jlab.org/tegwiki/index.php/HRS_Detector_Checkout_and_Calibration Detector Calibrations] (in parallel with other activities once we have the electron data)
 +
 +
</ol>

Latest revision as of 21:41, 12 January 2018

Back to 2018 Spring Run Plan Back to Tritium-Main

Installation and Configuration

With First Beam (2018-01-11 - 2018-01-12)

  1. Beamline
    1. Beam Centering
    2. Raster Size Calibration
    3. BPM Calibration (pedestal run, Bullseye scan)
    4. ARC Energy Measurement (parasitic only)
  2. DAQ and Trigger Checkout
  3. Detector Checkout / Optics
  4. Detector Calibrations (in parallel with other activities once we have the electron data)