Difference between revisions of "Run Meeting: February 23th, 2018"
Line 19: | Line 19: | ||
===Slides=== | ===Slides=== | ||
+ | Tritium elog: https://hallaweb.jlab.org/dvcslog/H3/ | ||
BlueJeans connection info: | BlueJeans connection info: |
Revision as of 14:05, 23 February 2018
Back to Main Page Daily_Run_Meetings
4:00PM Run Meeting, Counting house meeting room (200C)
Summary of past 24h:
- Smooth running with stable beam at ~22.2uA after recovery from the NL vacuum issue around 4pm. Opportunistic RF recovery for SL also took place during that downtime.
- During swing shift, we took empty cell data while MCC was trying to push for higher current for Hall C.
- Reached to 10k with He3 for kin#16 during owl shift.
- Downtime starting from 1pm for the cooling fan replacement for 1L22.
- Controlled access during the downtime: Jessie and techs went down to the Hall, Bill for raster check (https://logbooks.jlab.org/entry/3537043, https://logbooks.jlab.org/entry/3537195)
Plan: Back to production mode
Slides
Tritium elog: https://hallaweb.jlab.org/dvcslog/H3/
BlueJeans connection info:
To join the Meeting: https://bluejeans.com/372278653