Difference between revisions of "Run Meeting: March 1st, 2018"

From Tritium Experiments Group
Jump to navigation Jump to search
 
(16 intermediate revisions by 2 users not shown)
Line 1: Line 1:
Back to [[Main_Page|Main Page]] [[Daily_Run_Meetings]]
+
'''Back to:'''
 +
: [[Main_Page|Main Page]]
 +
: [[Daily_Run_Meetings|Daily Run Meetings]]
  
 
4:00PM Run Meeting, Counting house meeting room (200C)
 
4:00PM Run Meeting, Counting house meeting room (200C)
Line 7: Line 9:
  
 
==Summary of past 24h:==
 
==Summary of past 24h:==
 +
 +
'''Accelerator'''
 +
:Although it was improved, the number of trips increased yesterday because CEBAF tried to push >55uA to Hall C. They are back to normal.
 +
 
'''Swing shift'''
 
'''Swing shift'''
 +
:data production
 +
:beam off ~1h due to a box supply trip ---> https://logbooks.jlab.org/entry/3540483
  
 
'''Owl shift'''  
 
'''Owl shift'''  
 +
:data production
 +
:beam off ~30m due to a cavity failure ---> https://logbooks.jlab.org/entry/3540632
 +
 +
'''Day shift'''
 +
:data production
 +
  
'''Day shift'''  
+
<span style=color:red>'''DATA Status'''</span>
  
 +
Round VIII. Column 23/24. 2nd Tritium run
  
 
==Plan:==
 
==Plan:==
Line 32: Line 47:
 
:Beam back 16:00-17:00.
 
:Beam back 16:00-17:00.
  
 +
<span style=color:red>WIND ADVISORY POSSIBLE ISSUE (Chuck Long):</span> in case there is an alarm regarding the gas bottles HUT (not the bottles themselves), just take the key behind the racks and go to the gas bottles shed and press the low pressure button. There is a warning note in the Counting House.
  
 +
===Slides===
  
===Slides===
+
* Marco Carmignotto [https://wiki.jlab.org/tegwiki/index.php/File:PositronMarathon_MarcoCarmignotto_20180301.pdf Positron rates estimate for Marathon]
  
 
Tritium elog: https://hallaweb.jlab.org/dvcslog/H3/
 
Tritium elog: https://hallaweb.jlab.org/dvcslog/H3/

Latest revision as of 17:34, 1 March 2018

Back to:

Main Page
Daily Run Meetings

4:00PM Run Meeting, Counting house meeting room (200C)


RC: Carlos Ayerbe

Summary of past 24h:

Accelerator

Although it was improved, the number of trips increased yesterday because CEBAF tried to push >55uA to Hall C. They are back to normal.

Swing shift

data production
beam off ~1h due to a box supply trip ---> https://logbooks.jlab.org/entry/3540483

Owl shift

data production
beam off ~30m due to a cavity failure ---> https://logbooks.jlab.org/entry/3540632

Day shift

data production


DATA Status

Round VIII. Column 23/24. 2nd Tritium run

Plan:

Continue taking data and extend the columns

EXTRA:

Monday Beam Studies
Start 9:00 am
  • opportunistic beam.
    • FFB (2h)
  • Beam OFF
    • 'eta' tool devel (2h)
    • Optics (3h)
Beam back 16:00-17:00.

WIND ADVISORY POSSIBLE ISSUE (Chuck Long): in case there is an alarm regarding the gas bottles HUT (not the bottles themselves), just take the key behind the racks and go to the gas bottles shed and press the low pressure button. There is a warning note in the Counting House.

Slides

Tritium elog: https://hallaweb.jlab.org/dvcslog/H3/

BlueJeans connection info:

To join the Meeting: https://bluejeans.com/372278653