Difference between revisions of "Hyp-StraMeeting 20241205"
Jump to navigation
Jump to search
(→ERR) |
(→ERR) |
||
Line 18: | Line 18: | ||
** <sup>48</sup>Ca | ** <sup>48</sup>Ca | ||
** Detector spares? | ** Detector spares? | ||
− | *** | + | *** Counters <br> → Should be OK. |
*** Drift chambers<br> - No spare exists so far (→ Liguang will look for them). <br> → A plan to fix possible problems is necessary. | *** Drift chambers<br> - No spare exists so far (→ Liguang will look for them). <br> → A plan to fix possible problems is necessary. | ||
<br> → We need discussion with Mark as soon as possible. | <br> → We need discussion with Mark as soon as possible. |
Revision as of 08:48, 5 December 2024
Strategy Meeting (Hypernuclear Experiment)
Information
- Time and Date: 22:00 on Dec 5, 2024
- Participants: Joerg, Nue, Liguang, Pete, Sho, Guido, Toshi
- Place: Zoom
Contents
ERR
- The first ERR was done
- Discussion for reactions to the ERR report
- Radiation calculations will be done by Tokyo group by using FULKA and Geant4.
→ Sho installed FULKA in his laptop, and obtained a sample code for HKS from Pavel.
→ Sho will share the FULKA code with us, and Guido will work on it as well.
→ At first, we are going to ask Pavel to create the first code based on the latest design. - PCS
- English documents are not fully ready or are not in hand of JLab (reviewer etc).
- PCS test (+ existing power supplies) at JLab prior to the experiment
→ where/how/when/what to test?
- Target
- Possible dimension of CH2 will be clarified by us
- Necessary targets are already shown in ERR
- 48Ca
- Detector spares?
- Counters
→ Should be OK. - Drift chambers
- No spare exists so far (→ Liguang will look for them).
→ A plan to fix possible problems is necessary.
- Counters
- Radiation calculations will be done by Tokyo group by using FULKA and Geant4.
→ We need discussion with Mark as soon as possible.