Line 21: | Line 21: | ||
** May 24: Submission deadline | ** May 24: Submission deadline | ||
− | ===to the EER | + | ===to the first EER=== |
− | * PCS part → Request ERR by May 24, 2021. | + | * Finish the PCS part at first → Request ERR by May 24, 2021. |
* Other parts will be filled later. | * Other parts will be filled later. | ||
+ | * The 2nd ERR | ||
+ | ** Target system including cryogenic targets | ||
+ | ** Radiation budget | ||
==Next Strategy Meeting== | ==Next Strategy Meeting== |
Latest revision as of 07:34, 27 April 2021
Strategy Meeting
Info
- Apr 27, 2021
- Nue, Joerg, Pete, Liguang, Guido, Franco, Toshi, Sho, Bishnu, Suzuki, Okuyama, Itabashi, Kaneta, Mizuno, Akiyama, Fujiwara, Toyama
- Online
Status report
- New magnet (PCS) status: Nue
- Shipping takes 5 months in total.
- PCS will arrive at JLab in the latte half of this year.
→ We did not talk with JLab people yet about this.
Discussion
Proposal (C12-19-002): A = 3, 4 hypernuclear measurement at JLab Hall A): Toshi
- Target Meeting with Dave was held today (Target Meeting on Apr 27, 2021)
→ Dave will write the part of target design.
→ The density assumption is changed (increased!!)
→ Once Dave updates the values in the proposal, Toshi will update the various estimations. - Call for seeking collabrator → Google form?
- Timeline
- May 1-3: Start calling to ask to be collaboration members with the first draft (ver. March 2021)
- May 16: The 2nd version to be distributed
- May 23: Submission
- May 24: Submission deadline
to the first EER
- Finish the PCS part at first → Request ERR by May 24, 2021.
- Other parts will be filled later.
- The 2nd ERR
- Target system including cryogenic targets
- Radiation budget
Next Strategy Meeting