Back to 2017 Fall Run Plan Back to Tritium-Main
Installation and Configuration
Before Beam
- Trigger Timing Checkout (placeholder slides)
- HRS Detector Checkout
- Beamline
- Spectrometer Angles
- Magnets
- DAQ
- Software
With First Beam
- Beamline
- Beam Centering
- Raster Size Calibration
- BPM Calibration (pedestal run, Bullseye scan)
- BCM Calibration
- ARC Energy Measurement (parasitic only)
- DAQ and Trigger Checkout
- Detector Checkout with single foil, multi foils, and target cells
- Optics commissioning HRS Optics Run
- Target Boiling Study
- Detector Calibrations (in parallel with other activities once we have the electron data)