Difference between revisions of "Installation and Commissioning"
Jump to navigation
Jump to search
Line 5: | Line 5: | ||
=Before Beam (by 12/04/2017) = | =Before Beam (by 12/04/2017) = | ||
+ | |||
+ | {{font color|green|blue| This means "Done"}} | ||
+ | {{font color|red|yellow| This means "Ongoing Issues"}} | ||
+ | {{font color| | | This means "To-Do"}} | ||
+ | |||
* Trigger Timing Checkout [[:File:placeholder.pdf|(placeholder slides)]] | * Trigger Timing Checkout [[:File:placeholder.pdf|(placeholder slides)]] | ||
* [[ HRS Detector Checkout]] | * [[ HRS Detector Checkout]] |
Revision as of 09:55, 30 November 2017
Back to 2017 Fall Run Plan Back to Tritium-Main
Installation and Configuration
Before Beam (by 12/04/2017)
TEST TEST TEST
- Trigger Timing Checkout (placeholder slides)
- HRS Detector Checkout
- Beamline
- Spectrometer Angles
- Magnets
- DAQ
- Software
With First Beam (12/04/2017 - 12/10/2017
- Beamline
- Beam Centering
- Raster Size Calibration
- BPM Calibration (pedestal run, Bullseye scan)
- BCM Calibration
- ARC Energy Measurement (parasitic only)
- DAQ and Trigger Checkout
- Detector Checkout with single foil, multi foils, and target cells
- Optics commissioning HRS Optics Run
- Target Boiling Study
- Detector Calibrations (in parallel with other activities once we have the electron data)