Revision as of 14:28, 1 March 2018
Back to:
4:00PM Run Meeting, Counting house meeting room (200C)
RC: Carlos Ayerbe
Summary of past 24h:
Accelerator
- Although it was improved, the number of trips increased yesterday because CEBAF tried to push >55uA to Hall C. They are back to normal.
Swing shift
- data production
- beam off ~1h due to a box supply trip ---> https://logbooks.jlab.org/entry/3540483
Owl shift
- data production
- beam off ~30m due to a cavity failure ---> https://logbooks.jlab.org/entry/3540632
Day shift
- data production
DATA Status
Round VIII. Column 23/24. 2nd Tritium run
Plan:
Continue taking data and extend the columns
EXTRA:
- Monday Beam Studies
- Start 9:00 am
- opportunistic beam.
- FFB (2h)
- Beam OFF
- 'eta' tool devel (2h)
- Optics (3h)
- Beam back 16:00-17:00.
Slides
Tritium elog: https://hallaweb.jlab.org/dvcslog/H3/
BlueJeans connection info:
To join the Meeting: https://bluejeans.com/372278653