Difference between revisions of "Hyp-StraMeeting 20211007"
Jump to navigation
Jump to search
Line 7: | Line 7: | ||
==Status Report== | ==Status Report== | ||
− | === | + | ===Sho=== |
+ | * PCS | ||
+ | ** Will be delivered in Feb ~ Mar, 2022 | ||
− | * | + | *Solid Target |
+ | ** Multi foils possibility → need careful study of noise in the case of Hall C option. | ||
+ | ** Rough design for solid target ladder | ||
− | + | * Drawing for some cases of Hall C option | |
− | * | ||
− | |||
− | === | + | ===Toshi=== |
+ | * Some comments of S/N for Hall C experiment | ||
==Discussion== | ==Discussion== |
Revision as of 07:39, 7 October 2021
Strategy Meeting
Info
- 20:00- on Oct 07, 2021 (JST)
- via BlueJeans
Status Report
Sho
- PCS
- Will be delivered in Feb ~ Mar, 2022
- Solid Target
- Multi foils possibility → need careful study of noise in the case of Hall C option.
- Rough design for solid target ladder
- Drawing for some cases of Hall C option
Toshi
- Some comments of S/N for Hall C experiment
Discussion
Commissioning Schedule
- Is it possible to visit JLab to work on detectors?
Collaboration Meeting
- November--Dec, 2021