Difference between revisions of "Installation and Commissioning"
Jump to navigation
Jump to search
m (→Before Beam) |
|||
Line 4: | Line 4: | ||
=[[Installation and Configuration]]= | =[[Installation and Configuration]]= | ||
− | =Before Beam= | + | =Before Beam (by 12/04/2017) = |
* Trigger Timing Checkout [[:File:placeholder.pdf|(placeholder slides)]] | * Trigger Timing Checkout [[:File:placeholder.pdf|(placeholder slides)]] | ||
* [[ HRS Detector Checkout]] | * [[ HRS Detector Checkout]] |
Revision as of 09:47, 30 November 2017
Back to 2017 Fall Run Plan Back to Tritium-Main
Installation and Configuration
Before Beam (by 12/04/2017)
- Trigger Timing Checkout (placeholder slides)
- HRS Detector Checkout
- Beamline
- Spectrometer Angles
- Magnets
- DAQ
- Software
With First Beam
- Beamline
- Beam Centering
- Raster Size Calibration
- BPM Calibration (pedestal run, Bullseye scan)
- BCM Calibration
- ARC Energy Measurement (parasitic only)
- DAQ and Trigger Checkout
- Detector Checkout with single foil, multi foils, and target cells
- Optics commissioning HRS Optics Run
- Target Boiling Study
- Detector Calibrations (in parallel with other activities once we have the electron data)