Difference between revisions of "Additional Installation and Commissioning"

From Tritium Experiments Group
Jump to navigation Jump to search
Line 18: Line 18:
 
<li> [https://wiki.jlab.org/tegwiki/index.php/Data_Acquisition_System_and_Triggers DAQ and Trigger Checkout]
 
<li> [https://wiki.jlab.org/tegwiki/index.php/Data_Acquisition_System_and_Triggers DAQ and Trigger Checkout]
  
<li> [[Detector Checkout with single foil, multi foils, and target cells]]
+
<li> [https://wiki.jlab.org/tegwiki/index.php/Detector_Checkout_with_single_foil,_multi_foils,_and_target_cells Detector Checkout / Optics]
  
 
<li> [https://wiki.jlab.org/tegwiki/index.php/Optics_Calibration Optics commissioning HRS Optics Run]
 
<li> [https://wiki.jlab.org/tegwiki/index.php/Optics_Calibration Optics commissioning HRS Optics Run]

Revision as of 00:30, 12 January 2018

Back to 2018 Spring Run Plan Back to Tritium-Main

Installation and Configuration

With First Beam (12/04/2017 - 12/10/2017

  1. Beamline
    1. Beam Centering
    2. Raster Size Calibration
    3. BPM Calibration (pedestal run, Bullseye scan)
    4. ARC Energy Measurement (parasitic only)
  2. DAQ and Trigger Checkout
  3. Detector Checkout / Optics
  4. Optics commissioning HRS Optics Run
  5. Detector Calibrations (in parallel with other activities once we have the electron data)