* We can adapt the list tasks during the [https://wiki.jlab.org/tegwiki/index.php/Additional_Installation_and_Commissioning Spring 2018 run]
+
* We can link to the list tasks during the [https://wiki.jlab.org/tegwiki/index.php/Additional_Installation_and_Commissioning Spring 2018 run]
[https://wiki.jlab.org/tegwiki/index.php/2018_Srping_Run <B>Back to 2018 Spring Run Plan</B>]
+
* Create new Installation and Commissioning plan here.
  
 
=[[Installation and Configuration]]=
 
=[[Installation and Configuration]]=

Revision as of 13:13, 8 August 2018

Back to Tritium-Main Back to 2018 Fall Run Plan

  • We can link to the list tasks during the Spring 2018 run
  • Create new Installation and Commissioning plan here.

Installation and Configuration

With First Beam (2019-09-04 - 2019-09-10)

  1. Beamline
    1. Beam Centering
    2. Raster Size Calibration
    3. BPM Calibration (pedestal run, Bullseye scan)
    4. ARC Energy Measurement (parasitic only)
  2. DAQ and Trigger Checkout
  3. Detector Checkout / Optics
  4. Detector Calibrations (in parallel with other activities once we have the electron data)