Difference between revisions of "Fall Installation and Commissioning"
Jump to navigation
Jump to search
Line 19: | Line 19: | ||
</ol> | </ol> | ||
− | <li> [https://wiki.jlab.org/tegwiki/index.php/Data_Acquisition_System_and_Triggers DAQ and Trigger Checkout] | + | <li> [https://wiki.jlab.org/tegwiki/index.php/Data_Acquisition_System_and_Triggers DAQ and Trigger Checkout] (regular) |
− | <li> [ | + | <li> [[New Trigger Checkout]] |
− | <li> [https://wiki.jlab.org/tegwiki/index.php/HRS_Detector_Checkout_and_Calibration Detector Calibrations] (in parallel with other activities once we have the electron data) | + | <li> [https://wiki.jlab.org/tegwiki/index.php/Detector_Checkout_with_single_foil,_multi_foils,_and_target_cells Detector Checkout / Optics] (regular) |
+ | <li> [[New Detector / Optics Checkout]] | ||
+ | |||
+ | <li> [https://wiki.jlab.org/tegwiki/index.php/HRS_Detector_Checkout_and_Calibration Detector Calibrations] (in parallel with other activities once we have the electron data) (regular) | ||
+ | |||
+ | <li> [[New Detector Calibration]] | ||
</ol> | </ol> |
Revision as of 11:19, 13 August 2018
Back to Tritium-Main Back to 2018 Fall Run Plan
- We can link to the list tasks during the Spring 2018 run
- Create new Installation and Commissioning plan here.
Installation and Configuration
With First Beam (2019-09-04 - 2019-09-10)
- Beamline
- Beam Centering
- Raster Size Calibration
- BPM Calibration (pedestal run, Bullseye scan)
- ARC Energy Measurement (parasitic only)
- DAQ and Trigger Checkout (regular)
- New Trigger Checkout
- Detector Checkout / Optics (regular)
- New Detector / Optics Checkout
- Detector Calibrations (in parallel with other activities once we have the electron data) (regular)
- New Detector Calibration