Additional Installation and Commissioning

From Tritium Experiments Group
Revision as of 23:30, 11 January 2018 by Randallm (talk | contribs)
Jump to navigation Jump to search

Back to 2018 Spring Run Plan Back to Tritium-Main

Installation and Configuration

With First Beam (12/04/2017 - 12/10/2017

  1. Beamline
    1. Beam Centering
    2. Raster Size Calibration
    3. BPM Calibration (pedestal run, Bullseye scan)
    4. ARC Energy Measurement (parasitic only)
  2. DAQ and Trigger Checkout
  3. Detector Checkout / Optics
  4. Optics commissioning HRS Optics Run
  5. Detector Calibrations (in parallel with other activities once we have the electron data)