Fall Installation and Commissioning

From Tritium Experiments Group
Jump to navigation Jump to search

Back to Tritium-Main Back to 2018 Fall Run Plan

  • We can link to the list tasks during the Spring 2018 run
  • Create new Installation and Commissioning plan here.

Installation and Configuration

With First Beam (2019-09-04 - 2019-09-10)

  1. Beamline
    1. Beam Centering
    2. Raster Size Calibration
    3. BPM Calibration (pedestal run, Bullseye scan)
    4. ARC Energy Measurement (parasitic only)
  2. DAQ and Trigger Checkout (regular)
    1. New DAQ and Trigger Checkout
  3. Detector Checkout / Optics (regular)
    1. New Detector Checkout
    2. New Optics Checkout
  4. Detector Calibrations (in parallel with other activities once we have the electron data) (regular)
    1. New Detector Calibration