Difference between revisions of "Hyp-StraMeeting 20210427"

From Tritium Experiments Group
Jump to navigation Jump to search
 
(8 intermediate revisions by the same user not shown)
Line 3: Line 3:
 
==Info==
 
==Info==
 
* Apr 27, 2021
 
* Apr 27, 2021
* (Nue, Joerg, Pete, Liguang, Guido, Franco, Toshi)
+
* Nue, Joerg, Pete, Liguang, Guido, Franco, Toshi, Sho, Bishnu, Suzuki, Okuyama, Itabashi, Kaneta, Mizuno, Akiyama, Fujiwara, Toyama
 
* Online
 
* Online
  
 
==Status report==
 
==Status report==
 
* New magnet (PCS) status: Nue
 
* New magnet (PCS) status: Nue
 
+
** Shipping takes 5 months in total.
 +
** PCS will arrive at JLab in the latte half of this year. <br> &rarr; We did not talk with JLab people yet about this.
  
 
==Discussion==
 
==Discussion==
* Proposal (C12-19-002): A = 3, 4 hypernuclear measurement at JLab Hall A): Toshi
+
===Proposal (C12-19-002): A = 3, 4 hypernuclear measurement at JLab Hall A): Toshi===
** Target Meeting with Dave was held today <br> &rarr; Dave will write the part of target design. <br> &rarr; The density assumption is changed (increased!!) &rarr; Once Dave updates the values in the proposal, Toshi will update the various estimations.  
+
* Target Meeting with Dave was held today ([[HYP_Target_Meeting_20210427|Target Meeting on Apr 27, 2021]])<br> &rarr; Dave will write the part of target design. <br> &rarr; The density assumption is changed (increased!!) <br> &rarr; Once Dave updates the values in the proposal, Toshi will update the various estimations.  
 
* Call for seeking collabrator &rarr; Google form?  
 
* Call for seeking collabrator &rarr; Google form?  
 
* Timeline
 
* Timeline
Line 20: Line 21:
 
** May 24: Submission deadline
 
** May 24: Submission deadline
  
* to the EER
+
===to the first EER===
 +
* Finish the PCS part at first &rarr; Request ERR by May 24, 2021.
 +
* Other parts will be filled later.
 +
* The 2nd ERR
 +
** Target system including cryogenic targets
 +
** Radiation budget
  
 
==Next Strategy Meeting==
 
==Next Strategy Meeting==

Latest revision as of 07:34, 27 April 2021

Strategy Meeting

Info

  • Apr 27, 2021
  • Nue, Joerg, Pete, Liguang, Guido, Franco, Toshi, Sho, Bishnu, Suzuki, Okuyama, Itabashi, Kaneta, Mizuno, Akiyama, Fujiwara, Toyama
  • Online

Status report

  • New magnet (PCS) status: Nue
    • Shipping takes 5 months in total.
    • PCS will arrive at JLab in the latte half of this year.
      → We did not talk with JLab people yet about this.

Discussion

Proposal (C12-19-002): A = 3, 4 hypernuclear measurement at JLab Hall A): Toshi

  • Target Meeting with Dave was held today (Target Meeting on Apr 27, 2021)
    → Dave will write the part of target design.
    → The density assumption is changed (increased!!)
    → Once Dave updates the values in the proposal, Toshi will update the various estimations.
  • Call for seeking collabrator → Google form?
  • Timeline
    • May 1-3: Start calling to ask to be collaboration members with the first draft (ver. March 2021)
    • May 16: The 2nd version to be distributed
    • May 23: Submission
    • May 24: Submission deadline

to the first EER

  • Finish the PCS part at first → Request ERR by May 24, 2021.
  • Other parts will be filled later.
  • The 2nd ERR
    • Target system including cryogenic targets
    • Radiation budget

Next Strategy Meeting




Back to Home (Hypernuclear project with HRS-HKS)