Installation and Commissioning
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Back to 2017 Fall Run Plan Back to Tritium-Main
Installation and Configuration
Before Beam (by 12/04/2017)
- Trigger Timing Checkout (placeholder slides)
- HRS Detector Checkout
- Beamline
- Spectrometer Angles
- Magnets
- DAQ
- Software
With First Beam (12/04/2017 - 12/10/2017
- Beamline
- Beam Centering
- Raster Size Calibration
- BPM Calibration (pedestal run, Bullseye scan)
- BCM Calibration
- ARC Energy Measurement (parasitic only)
- DAQ and Trigger Checkout
- Detector Checkout with single foil, multi foils, and target cells
- Optics commissioning HRS Optics Run
- Target Boiling Study
- Detector Calibrations (in parallel with other activities once we have the electron data)