Difference between revisions of "April 6, 2016 - Monthly 4-laser Upgrade Status Meeting"
Jump to navigation
Jump to search
Line 3: | Line 3: | ||
=== Schedule (Joe) === | === Schedule (Joe) === | ||
* [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD] | * [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD] | ||
+ | ** Apr 06 - Apr 27 : Halls A/B/D | ||
+ | ** Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing | ||
+ | ** May 13 - Jun 27 : PRAD / Bubble runs | ||
+ | * Phase I : Jun 27 – July 25 | ||
+ | **Construct 4th laser, modify laser table for 4-beam combination, include new EO pulse scheme | ||
+ | **Install 4-beam SCAM, laser macro-pulse chassis, PSS laser shutter chassis | ||
+ | **INJ lock-ups TBD for commissioning | ||
+ | *Phase II : Jul 26 – Aug 19 | ||
+ | **Contingency for Phase I | ||
+ | **Replace 3-channel VME SRF-style digital LLRF with 4-channel PC104 laser dedicated digital LLRF w/ 250/499 | ||
+ | **INJ and INJ/NL lock-ups TBD for commissioning | ||
=== Laser Status (John) === | === Laser Status (John) === | ||
Line 18: | Line 29: | ||
=== LLRF (Tomasz) === | === LLRF (Tomasz) === | ||
− | * Implementation timeline | + | * March 14 - Draft of source requirements circulated [[media:LLRF-Source_v1.docx]] |
+ | Implementation timeline |
Revision as of 12:17, 5 April 2016
We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.
Schedule (Joe)
- Summer SAD
- Apr 06 - Apr 27 : Halls A/B/D
- Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
- May 13 - Jun 27 : PRAD / Bubble runs
- Phase I : Jun 27 – July 25
- Construct 4th laser, modify laser table for 4-beam combination, include new EO pulse scheme
- Install 4-beam SCAM, laser macro-pulse chassis, PSS laser shutter chassis
- INJ lock-ups TBD for commissioning
- Phase II : Jul 26 – Aug 19
- Contingency for Phase I
- Replace 3-channel VME SRF-style digital LLRF with 4-channel PC104 laser dedicated digital LLRF w/ 250/499
- INJ and INJ/NL lock-ups TBD for commissioning
Laser Status (John)
- Status
SCAM-II (Roger)
- March
- Additional input from Kevin Jordan and Michael Tiefenback collected.
- Grames met with Injector group, solicited pre-draft input
- March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
- April
- Hansknecht and Robertson provided feedback
- Flood/Grames reviewed feedback and refined document punch list
- April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review
LLRF (Tomasz)
- March 14 - Draft of source requirements circulated media:LLRF-Source_v1.docx
Implementation timeline