=== Schedule (Joe) === | === Schedule (Joe) === | ||
* [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD] | * [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD] | ||
+ | ** Apr 06 - Apr 27 : Halls A/B/D | ||
+ | ** Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing | ||
+ | ** May 13 - Jun 27 : PRAD / Bubble runs | ||
+ | ** Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests | ||
+ | ** Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF | ||
+ | ** Aug 19 - Sep 1 : Bubble Run II | ||
+ | ** Sep 2 - 20 : PSS Cert | ||
+ | ** Oct 1 : Fall Run Begins | ||
=== Laser Status (John) === | === Laser Status (John) === | ||
Line 8: | Line 16: | ||
=== SCAM-II (Roger) === | === SCAM-II (Roger) === | ||
− | * | + | * March |
+ | ** Additional input from Kevin Jordan and Michael Tiefenback collected. | ||
+ | ** Grames met with Injector group, solicited pre-draft input | ||
+ | ** March 31st - Version 1 draft circulated [[media:SAMII_v1.docx]] to Flood, Hansknecht, Robertson, Higgins | ||
+ | * April | ||
+ | ** Hansknecht and Robertson provided feedback | ||
+ | ** Flood/Grames reviewed feedback and refined document punch list | ||
+ | ** April 5th - Version 2 draft [[media:SAMII_v2.docx]] circulated to larger group for review | ||
=== LLRF (Tomasz) === | === LLRF (Tomasz) === | ||
− | * Implementation timeline | + | * Grames met with Injector group, verified there are no bunch length hooks into LLRF, use phase shifters |
+ | * March 14 - Draft of source requirements circulated [[media:LLRF-Source_v1.docx]] | ||
+ | * Implementation timeline [[media:4Laser_LLRF_overview.ppt]] |
Latest revision as of 10:52, 6 April 2016
We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.
Schedule (Joe)
- Summer SAD
- Apr 06 - Apr 27 : Halls A/B/D
- Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
- May 13 - Jun 27 : PRAD / Bubble runs
- Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests
- Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF
- Aug 19 - Sep 1 : Bubble Run II
- Sep 2 - 20 : PSS Cert
- Oct 1 : Fall Run Begins
Laser Status (John)
- Status
SCAM-II (Roger)
- March
- Additional input from Kevin Jordan and Michael Tiefenback collected.
- Grames met with Injector group, solicited pre-draft input
- March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
- April
- Hansknecht and Robertson provided feedback
- Flood/Grames reviewed feedback and refined document punch list
- April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review
LLRF (Tomasz)
- Grames met with Injector group, verified there are no bunch length hooks into LLRF, use phase shifters
- March 14 - Draft of source requirements circulated media:LLRF-Source_v1.docx
- Implementation timeline media:4Laser_LLRF_overview.ppt