** Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing | ** Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing | ||
** May 13 - Jun 27 : PRAD / Bubble runs | ** May 13 - Jun 27 : PRAD / Bubble runs | ||
− | * | + | ** Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests |
− | + | ** Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF | |
− | + | ** Aug 19 - Sep 1 : Bubble Run II | |
− | ** | + | ** Sep 2 - 20 : PSS Cert |
− | + | ** Oct 1 : Fall Run Begins | |
− | ** | ||
− | ** | ||
− | ** | ||
=== Laser Status (John) === | === Laser Status (John) === | ||
Line 29: | Line 26: | ||
=== LLRF (Tomasz) === | === LLRF (Tomasz) === | ||
+ | * Grames met with Injector group, verified there are no bunch length hooks into LLRF, use phase shifters | ||
* March 14 - Draft of source requirements circulated [[media:LLRF-Source_v1.docx]] | * March 14 - Draft of source requirements circulated [[media:LLRF-Source_v1.docx]] | ||
− | Implementation timeline | + | * Implementation timeline [[media:4Laser_LLRF_overview.ppt]] |
Latest revision as of 10:52, 6 April 2016
We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.
Schedule (Joe)
- Summer SAD
- Apr 06 - Apr 27 : Halls A/B/D
- Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
- May 13 - Jun 27 : PRAD / Bubble runs
- Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests
- Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF
- Aug 19 - Sep 1 : Bubble Run II
- Sep 2 - 20 : PSS Cert
- Oct 1 : Fall Run Begins
Laser Status (John)
- Status
SCAM-II (Roger)
- March
- Additional input from Kevin Jordan and Michael Tiefenback collected.
- Grames met with Injector group, solicited pre-draft input
- March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
- April
- Hansknecht and Robertson provided feedback
- Flood/Grames reviewed feedback and refined document punch list
- April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review
LLRF (Tomasz)
- Grames met with Injector group, verified there are no bunch length hooks into LLRF, use phase shifters
- March 14 - Draft of source requirements circulated media:LLRF-Source_v1.docx
- Implementation timeline media:4Laser_LLRF_overview.ppt