**Replace 3-channel VME SRF-style digital LLRF with 4-channel PC104 laser dedicated digital LLRF w/ 250/499
 
**Replace 3-channel VME SRF-style digital LLRF with 4-channel PC104 laser dedicated digital LLRF w/ 250/499
 
**INJ and INJ/NL lock-ups TBD for commissioning
 
**INJ and INJ/NL lock-ups TBD for commissioning
 +
* PSS Cert : Sep 2 - 20
 +
* Fall Run Begins : Oct 1
  
 
=== Laser Status (John) ===
 
=== Laser Status (John) ===

Revision as of 10:49, 6 April 2016

We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.

Schedule (Joe)

  • Summer SAD
    • Apr 06 - Apr 27 : Halls A/B/D
    • Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
    • May 13 - Jun 27 : PRAD / Bubble runs
  • Summer SAD Phase I : Jun 27 – July 25
    • Construct 4th laser, modify laser table for 4-beam combination, include new EO pulse scheme
    • Install 4-beam SCAM, laser macro-pulse chassis, PSS laser shutter chassis
    • INJ lock-ups TBD for commissioning
  • Summer SAD Phase II : Jul 26 – Aug 19
    • Contingency for Phase I
    • Replace 3-channel VME SRF-style digital LLRF with 4-channel PC104 laser dedicated digital LLRF w/ 250/499
    • INJ and INJ/NL lock-ups TBD for commissioning
  • PSS Cert : Sep 2 - 20
  • Fall Run Begins : Oct 1

Laser Status (John)

  • Status

SCAM-II (Roger)

  • March
    • Additional input from Kevin Jordan and Michael Tiefenback collected.
    • Grames met with Injector group, solicited pre-draft input
    • March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
  • April
    • Hansknecht and Robertson provided feedback
    • Flood/Grames reviewed feedback and refined document punch list
    • April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review

LLRF (Tomasz)