(Created page with "We will meet Wed April 6 @ 11am in TL-1227 for monthly status update. === Schedule (Joe) === * [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD] === La...")
 
 
(10 intermediate revisions by the same user not shown)
Line 2: Line 2:
  
 
=== Schedule (Joe) ===
 
=== Schedule (Joe) ===
* [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD]  
+
* [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD]  
 +
** Apr 06 - Apr 27 : Halls A/B/D
 +
** Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
 +
** May 13 - Jun 27 : PRAD / Bubble runs
 +
** Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests
 +
** Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF
 +
** Aug 19 - Sep 1 : Bubble Run II
 +
** Sep 2 - 20 : PSS Cert
 +
** Oct 1 : Fall Run Begins
  
 
=== Laser Status (John) ===
 
=== Laser Status (John) ===
* Status
+
* Status
  
 
=== SCAM-II (Roger) ===
 
=== SCAM-II (Roger) ===
* Requirements document
+
* March
 +
** Additional input from Kevin Jordan and Michael Tiefenback collected.
 +
** Grames met with Injector group, solicited pre-draft input
 +
** March 31st - Version 1 draft circulated [[media:SAMII_v1.docx]] to Flood, Hansknecht, Robertson, Higgins
 +
* April
 +
** Hansknecht and Robertson provided feedback
 +
** Flood/Grames reviewed feedback and refined document punch list
 +
** April 5th - Version 2 draft [[media:SAMII_v2.docx]] circulated to larger group for review
  
 
=== LLRF (Tomasz) ===
 
=== LLRF (Tomasz) ===
* Implementation timeline
+
* Grames met with Injector group, verified there are no bunch length hooks into LLRF, use phase shifters
 +
* March 14 - Draft of source requirements circulated [[media:LLRF-Source_v1.docx]]
 +
* Implementation timeline [[media:4Laser_LLRF_overview.ppt]]

Latest revision as of 10:52, 6 April 2016

We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.

Schedule (Joe)

  • Summer SAD
    • Apr 06 - Apr 27 : Halls A/B/D
    • Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
    • May 13 - Jun 27 : PRAD / Bubble runs
    • Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests
    • Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF
    • Aug 19 - Sep 1 : Bubble Run II
    • Sep 2 - 20 : PSS Cert
    • Oct 1 : Fall Run Begins

Laser Status (John)

  • Status

SCAM-II (Roger)

  • March
    • Additional input from Kevin Jordan and Michael Tiefenback collected.
    • Grames met with Injector group, solicited pre-draft input
    • March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
  • April
    • Hansknecht and Robertson provided feedback
    • Flood/Grames reviewed feedback and refined document punch list
    • April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review

LLRF (Tomasz)