=== Pre-assembly ===
+
=== Pre-assembly - COMPLETE (5/27/2022) ===
  
 
* Reflector pre-shaping procedure and material
 
* Reflector pre-shaping procedure and material
Line 21: Line 21:
 
* Crystal Wrapping Documentation
 
* Crystal Wrapping Documentation
 
::* [https://docs.google.com/spreadsheets/d/11tthz375eiESTezsGdbkZbNq6eGj3ssPKPLIYQ9iE0A/edit#gid=2133090489 Crystal ID Documentation]
 
::* [https://docs.google.com/spreadsheets/d/11tthz375eiESTezsGdbkZbNq6eGj3ssPKPLIYQ9iE0A/edit#gid=2133090489 Crystal ID Documentation]
 +
::* [https://wiki.jlab.org/cuawiki/images/7/7c/PWO_wrapping.pdf Pictures from crystal wrapping]
  
 
=== Assembly ===
 
=== Assembly ===

Revision as of 08:08, 24 June 2022

Task List 2022

  • Link to the Google Doc

Resource List

Pre-assembly - COMPLETE (5/27/2022)

  • Reflector pre-shaping procedure and material
  • Crystal Wrapping Procedure Link
  • To be completed in May 2022
  • On site personnel: AANL (2), CUA (3), MSU (1), UIC (1), DSG (1-2, at the end of May)
  • Crystal Wrapping Documentation

Assembly

  • planned for June 2022
  • onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), ODU (1), OU (1-2), U. Glasgow (TBD)
  • planned for July/August
  • onsite personnel: OU (1-2), ODU (1), AANL (2), CUA (2-3), U. Glasgow (TBD)

Mechanical

  • NPS Deck Pictures (April 2022)
  • NPS Deck Pictures (March 2022)

Magnet

Crystals

  • Overview of crystal properties

DAQ/Electronics/Analyzer

  • GitHub link (contact Brad, Carlos Y., or Steve W. for access)