Difference between revisions of "NPS Assembly"
Jump to navigation
Jump to search
Line 26: | Line 26: | ||
* [http://www.jlab.org/~munoz/NPS_mounting_procedure.pptx Assembly Procedure Steps] | * [http://www.jlab.org/~munoz/NPS_mounting_procedure.pptx Assembly Procedure Steps] | ||
− | ::* | + | ::* multiple phases: |
+ | :::* crystal stacking | ||
+ | :::* PMT block assembly | ||
+ | :::* cabling and installation of the big PCBs | ||
+ | :::* preparation for detector checkout | ||
+ | :::* detector checkout | ||
+ | ::* [https://wiki.jlab.org/cuawiki/images/6/67/Time_mounting_graph.xlsx Assembly time estimate] | ||
+ | |||
+ | ::* Crystal stacking - COMPLETE (10 June 2022) | ||
::* onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2) | ::* onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2) | ||
− | ::* [https://wiki.jlab.org/cuawiki/images/ | + | ::* All crystals are stacked and 4 full columns of PMTs and electronics are cabled - assembled [https://wiki.jlab.org/cuawiki/images/7/7b/Nps0.jpeg NPS picture] |
+ | |||
+ | * Preparation for detector checkout - planned for July/August | ||
+ | ::* onsite personnel: AANL (2), CUA (1-2), OU (2-3); onsite contacts: Brad, Julie/Paul, Carlos | ||
+ | ::* In order to perform the detector tests, there is work to be done outside the calorimeter box: | ||
+ | :::* HV cables, signal cables and LV cables need to be put in place and hooked to the DAQ, which needs to be setup. | ||
+ | :::* Power supplies (HV, LV) need to be setup. | ||
+ | :::* Same for slow controls (for HV and LED), etc. | ||
− | * | + | * Detector Checkout |
− | ::* | + | ::* onsite personnel: OU (1-2), AANL (2), CUA (1-2), U. Glasgow (3); onsite contacts: Brad, David H. |
− | + | ::* [https://wiki.jlab.org/cuawiki/index.php/NPS_DAQ/Electronics_and_Analyzer_Meeting_(online,_2/25_2022) Detector checkout plans and task lists] | |
− | |||
− | |||
− | |||
* [https://wiki.jlab.org/cuawiki/images/b/b7/NPS-module-assembly-tracking-sheet_v2.xlsx NPS module assembly tracking spreadsheet] | * [https://wiki.jlab.org/cuawiki/images/b/b7/NPS-module-assembly-tracking-sheet_v2.xlsx NPS module assembly tracking spreadsheet] |
Revision as of 08:29, 24 June 2022
Task List 2022
- Link to the Google Doc
Resource List
Pre-assembly - COMPLETE (5/27/2022)
- Reflector pre-shaping procedure and material
- Crystal Wrapping Procedure Link
- To be completed in May 2022
- On site personnel: AANL (2), CUA (3), MSU (1), UIC (1), DSG (1-2, at the end of May)
- Crystal Wrapping Documentation
Assembly
- multiple phases:
- crystal stacking
- PMT block assembly
- cabling and installation of the big PCBs
- preparation for detector checkout
- detector checkout
- Crystal stacking - COMPLETE (10 June 2022)
- onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2)
- All crystals are stacked and 4 full columns of PMTs and electronics are cabled - assembled NPS picture
- Preparation for detector checkout - planned for July/August
- onsite personnel: AANL (2), CUA (1-2), OU (2-3); onsite contacts: Brad, Julie/Paul, Carlos
- In order to perform the detector tests, there is work to be done outside the calorimeter box:
- HV cables, signal cables and LV cables need to be put in place and hooked to the DAQ, which needs to be setup.
- Power supplies (HV, LV) need to be setup.
- Same for slow controls (for HV and LED), etc.
- Detector Checkout
- onsite personnel: OU (1-2), AANL (2), CUA (1-2), U. Glasgow (3); onsite contacts: Brad, David H.
- Detector checkout plans and task lists
Mechanical
- NPS Deck Pictures (April 2022)
- NPS Deck Pictures (March 2022)
Magnet
Crystals
- Overview of crystal properties
- spreadsheet from CRYTUR (January 2022) (dimensions, transmittance, light yield, radiation hardness)
DAQ/Electronics/Analyzer
- Link to DAQ/Electronics/Analyzer Meetings Meetings. Contact David Hamilton for details.
- GitHub link (contact Brad, Carlos Y., or Steve W. for access)