Line 17: | Line 17: | ||
* Crystal Wrapping Procedure [https://wiki.jlab.org/cuawiki/index.php/Wrapping_procedure Link] | * Crystal Wrapping Procedure [https://wiki.jlab.org/cuawiki/index.php/Wrapping_procedure Link] | ||
::* To be completed in May 2022 | ::* To be completed in May 2022 | ||
− | ::* On site personnel: AANL (2), CUA ( | + | ::* On site personnel: AANL (2), CUA (3), MSU (1), UIC (1), DSG (1-2, at the end of May) |
* Crystal Wrapping Documentation | * Crystal Wrapping Documentation |
Revision as of 08:05, 24 June 2022
Task List 2022
- Link to the Google Doc
Resource List
Pre-assembly
- Reflector pre-shaping procedure and material
- Crystal Wrapping Procedure Link
- To be completed in May 2022
- On site personnel: AANL (2), CUA (3), MSU (1), UIC (1), DSG (1-2, at the end of May)
- Crystal Wrapping Documentation
Assembly
- planned for June 2022
- onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), ODU (1), OU (1-2), U. Glasgow (TBD)
- planned for July/August
- onsite personnel: OU (1-2), ODU (1), AANL (2), CUA (2-3), U. Glasgow (TBD)
Mechanical
- NPS Deck Pictures (April 2022)
- NPS Deck Pictures (March 2022)
Magnet
Crystals
- Overview of crystal properties
- spreadsheet from CRYTUR (January 2022) (dimensions, transmittance, light yield, radiation hardness)
DAQ/Electronics/Analyzer
- Link to DAQ/Electronics/Analyzer Meetings Meetings. Contact David Hamilton for details.
- GitHub link (contact Brad, Carlos Y., or Steve W. for access)