NPS Assembly
Task List 2022
- Link to the Google Doc
Resource List
Pre-assembly - COMPLETE (5/27/2022)
- Reflector pre-shaping procedure and material
- Crystal Wrapping Procedure Link
- To be completed in May 2022
- On site personnel: AANL (2), CUA (3), MSU (1), UIC (1), DSG (1-2, at the end of May)
- Crystal Wrapping Documentation
Assembly
- Multiple phases:
- crystal stacking
- PMT block assembly
- cabling and installation of the big PCBs
- preparation for detector checkout
- detector checkout
- Crystal stacking - COMPLETE (10 June 2022)
- onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2); onsite contacts: Carlos, Vladimir, Brad
- All crystals are stacked and 4 full columns of PMTs and electronics are cabled - assembled NPS picture
- Preparation for detector checkout - planned for July/August
- onsite personnel: AANL (2), CUA (1-2), OU (2-3); onsite contacts: Brad, Julie/Paul, Carlos
- In order to perform the detector tests, there is work to be done outside the calorimeter box:
- HV cables, signal cables and LV cables need to be put in place and hooked to the DAQ, which needs to be setup.
- Power supplies (HV, LV) need to be setup.
- Same for slow controls (for HV and LED), etc.
- Detector Checkout - planned for August
- onsite personnel: OU (1-2), AANL (2), CUA (1-2), U. Glasgow (3); onsite contacts: Brad, David H.
- Detector checkout plans and task lists
Mechanical
- NPS Deck Pictures (April 2022)
- NPS Deck Pictures (March 2022)
Magnet
Crystals
- Overview of crystal properties
- spreadsheet from CRYTUR (January 2022) (dimensions, transmittance, light yield, radiation hardness)
DAQ/Electronics/Analyzer
- Link to DAQ/Electronics/Analyzer Meetings Meetings. Contact David Hamilton for details.
- GitHub link (contact Brad, Carlos Y., or Steve W. for access)