Difference between revisions of "NPS Assembly"

From Cuawiki
Jump to navigation Jump to search
Line 26: Line 26:
  
 
* [http://www.jlab.org/~munoz/NPS_mounting_procedure.pptx Assembly Procedure Steps]
 
* [http://www.jlab.org/~munoz/NPS_mounting_procedure.pptx Assembly Procedure Steps]
::* planned for June 2022
+
::* planned for June 2022  
::* onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), ODU (1), OU (1-2), U. Glasgow (TBD)
+
::* onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2)
 +
::* [https://wiki.jlab.org/cuawiki/images/6/67/Time_mounting_graph.xlsx Assembly time estimate]
  
* [https://wiki.jlab.org/cuawiki/images/6/67/Time_mounting_graph.xlsx Assembly time estimate]
+
* Assembly Status 6/10/2022
 +
::* Stacking complete [https://wiki.jlab.org/cuawiki/images/7/7b/Nps0.jpeg NPS picture]
 +
::* Three columns cabled and available for detector checkout
  
 
* [https://wiki.jlab.org/cuawiki/index.php/NPS_DAQ/Electronics_and_Analyzer_Meeting_(online,_2/25_2022) Detector checkout plans and task lists]
 
* [https://wiki.jlab.org/cuawiki/index.php/NPS_DAQ/Electronics_and_Analyzer_Meeting_(online,_2/25_2022) Detector checkout plans and task lists]
 
::* planned for July/August
 
::* planned for July/August
::* onsite personnel: OU (1-2), ODU (1), AANL (2), CUA (2-3), U. Glasgow (TBD)
+
::* onsite personnel: OU (1-2), ODU (1), AANL (2), CUA (2-3), U. Glasgow (3)
  
 
* [https://wiki.jlab.org/cuawiki/images/b/b7/NPS-module-assembly-tracking-sheet_v2.xlsx NPS module assembly tracking spreadsheet]
 
* [https://wiki.jlab.org/cuawiki/images/b/b7/NPS-module-assembly-tracking-sheet_v2.xlsx NPS module assembly tracking spreadsheet]

Revision as of 09:17, 24 June 2022

Task List 2022

  • Link to the Google Doc

Resource List

Pre-assembly - COMPLETE (5/27/2022)

  • Reflector pre-shaping procedure and material
  • Crystal Wrapping Procedure Link
  • To be completed in May 2022
  • On site personnel: AANL (2), CUA (3), MSU (1), UIC (1), DSG (1-2, at the end of May)
  • Crystal Wrapping Documentation

Assembly

  • planned for June 2022
  • onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2)
  • Assembly time estimate
  • Assembly Status 6/10/2022
  • Stacking complete NPS picture
  • Three columns cabled and available for detector checkout
  • planned for July/August
  • onsite personnel: OU (1-2), ODU (1), AANL (2), CUA (2-3), U. Glasgow (3)

Mechanical

  • NPS Deck Pictures (April 2022)
  • NPS Deck Pictures (March 2022)

Magnet

Crystals

  • Overview of crystal properties

DAQ/Electronics/Analyzer

  • GitHub link (contact Brad, Carlos Y., or Steve W. for access)