Difference between revisions of "February 28th, 2023"
Jump to navigation
Jump to search
(12 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | <b>Attended</b>: | + | <b>Attended</b>: ''Moskov'', ''Mikhail'', ''Justin'', ''Sean'', ''Hovanes'', and ''Igor''. Today, ''Jim'' is in a finding commission. |
* ''Moskov'' proposed to think about ERR-I in March/April [https://wiki.jlab.org/klproject/index.php/KLF_Phase_I_ERR]. | * ''Moskov'' proposed to think about ERR-I in March/April [https://wiki.jlab.org/klproject/index.php/KLF_Phase_I_ERR]. | ||
Line 7: | Line 7: | ||
* On February 27th, we had a meeting with FNAL folks to discuss a possibility to use FNAL EPB dipole for the CPS. | * On February 27th, we had a meeting with FNAL folks to discuss a possibility to use FNAL EPB dipole for the CPS. | ||
− | * Questions from Dave Harding: | + | * Questions from ''Dave Harding'': |
:* What is your schedule? When would you need the magnet? | :* What is your schedule? When would you need the magnet? | ||
:* Should we assume that this is a permanent installation rather than a loan? | :* Should we assume that this is a permanent installation rather than a loan? | ||
:* Would the magnet go straight to JLab? The issue here is making sure that whatever organization receives the magnet has the appropriate licenses to handle the (very slightly) radioactive material. | :* Would the magnet go straight to JLab? The issue here is making sure that whatever organization receives the magnet has the appropriate licenses to handle the (very slightly) radioactive material. | ||
:* Given the current condition of the magnets that we do not consider ready spares, would you want us to refurbish the selected magnet to our current standards? | :* Given the current condition of the magnets that we do not consider ready spares, would you want us to refurbish the selected magnet to our current standards? | ||
− | :* Do you have any special requirements on the power and water connections? I’m attaching a photo of one such magnet that we refurbished last year so you can get a feeling for our standard configuration. | + | :* Do you have any special requirements on the power and water connections? [https://wiki.jlab.org/klproject/images/a/a7/20220302_121838.jpg I’m attaching a photo of one such magnet that we refurbished last year so you can get a feeling for our standard configuration]. |
:* Would you want our beam tube left in place? | :* Would you want our beam tube left in place? | ||
:* Would you need a spare magnet? | :* Would you need a spare magnet? | ||
− | + | * [https://wiki.jlab.org/klproject/images/b/be/FNALMEETING022723.pdf ''Vitaly's'' slides] | |
+ | |||
+ | |||
+ | * On February 27th, we had a ''Hovanes'' CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [https://wiki.jlab.org/klproject/index.php/CPS_meeting_-_February_27,_2023]. | ||
+ | :* [[media:cps_absorber_temp_tim_02_27_23.pdf | Temperature calculations]] (''Tim''). | ||
+ | :* [[media:CPSKPTPRESENT022723.pdf | Radiation and Current Leakage between winding in Coil Return Area]] ''Vitaly's'' model. | ||
+ | |||
* On February 20th, we had a ''Hovanes'' CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [https://wiki.jlab.org/klproject/index.php/CPS_meeting_-_February_20,_2023]. | * On February 20th, we had a ''Hovanes'' CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [https://wiki.jlab.org/klproject/index.php/CPS_meeting_-_February_20,_2023]. | ||
:* Temperature calculations (''Tim''). | :* Temperature calculations (''Tim''). | ||
:* Review of ''Vitaly's'' model. | :* Review of ''Vitaly's'' model. | ||
+ | |||
* On February 6th, we had a ''Hovanes'' CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [https://wiki.jlab.org/klproject/index.php/CPS_meeting_-_February_6,_2023]. | * On February 6th, we had a ''Hovanes'' CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [https://wiki.jlab.org/klproject/index.php/CPS_meeting_-_February_6,_2023]. | ||
:* [https://wiki.jlab.org/klproject/images/7/77/Temp_calc_cps_02_06_2023.pdf Temperature calculations] (''Tim''). | :* [https://wiki.jlab.org/klproject/images/7/77/Temp_calc_cps_02_06_2023.pdf Temperature calculations] (''Tim''). | ||
:* Review of ''Vitaly's'' model. | :* Review of ''Vitaly's'' model. | ||
+ | |||
* On February 9th, we had a ''Hovanes'' KPT meeting for to prepare for ERR-I [https://wiki.jlab.org/klproject/index.php/KLF_Phase_I_ERR]. | * On February 9th, we had a ''Hovanes'' KPT meeting for to prepare for ERR-I [https://wiki.jlab.org/klproject/index.php/KLF_Phase_I_ERR]. |
Latest revision as of 09:22, 28 February 2023
Attended: Moskov, Mikhail, Justin, Sean, Hovanes, and Igor. Today, Jim is in a finding commission.
- Moskov proposed to think about ERR-I in March/April [1].
- Moskov proposed to think about a 7th KLF Collaboration Meeting in May/June after ERR-!.
- On February 27th, we had a meeting with FNAL folks to discuss a possibility to use FNAL EPB dipole for the CPS.
- Questions from Dave Harding:
- What is your schedule? When would you need the magnet?
- Should we assume that this is a permanent installation rather than a loan?
- Would the magnet go straight to JLab? The issue here is making sure that whatever organization receives the magnet has the appropriate licenses to handle the (very slightly) radioactive material.
- Given the current condition of the magnets that we do not consider ready spares, would you want us to refurbish the selected magnet to our current standards?
- Do you have any special requirements on the power and water connections? I’m attaching a photo of one such magnet that we refurbished last year so you can get a feeling for our standard configuration.
- Would you want our beam tube left in place?
- Would you need a spare magnet?
- On February 27th, we had a Hovanes CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [2].
- Temperature calculations (Tim).
- Radiation and Current Leakage between winding in Coil Return Area Vitaly's model.
- On February 20th, we had a Hovanes CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [3].
- Temperature calculations (Tim).
- Review of Vitaly's model.
- On February 6th, we had a Hovanes CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [4].
- Temperature calculations (Tim).
- Review of Vitaly's model.
- On February 9th, we had a Hovanes KPT meeting for to prepare for ERR-I [5].