<li> [https://wiki.jlab.org/tegwiki/index.php/HRS_Detector_Checkout_and_Calibration Detector Calibrations] (in parallel with other activities once we have the electron data) (regular) | <li> [https://wiki.jlab.org/tegwiki/index.php/HRS_Detector_Checkout_and_Calibration Detector Calibrations] (in parallel with other activities once we have the electron data) (regular) |
Revision as of 14:13, 21 September 2018
Back to Tritium-Main Back to 2018 Fall Run Plan
- We can link to the list tasks during the Spring 2018 run
- Create new Installation and Commissioning plan here.
New Installation and Configuration
With First Beam (2019-09-04 - 2019-09-10)
- Beamline
- Beam Centering (standard)
- Raster Size Calibration (standard)
- ARC Energy Measurement (standard, parasitic only)
- Fall-2018 BPM Calibration (See Spring2018 BPM Calibration) (pedestal run, Bullseye scan)
- DAQ and Trigger Checkout (regular)
- Detector Checkout / Optics (regular)
- Detector Calibrations (in parallel with other activities once we have the electron data) (regular)
- Fall-2018 Target Boiling Study