== Quick Phase 1 Links == | == Quick Phase 1 Links == | ||
− | + | : ATLIS => [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21170 Phase 1 ATLIS] | |
− | + | : 8:30 Tools => [[CIS Phase 1 work plans]] | |
− | + | : HCO => [[Phase 1 - HCO & Commissioning]] | |
− | + | : Meetings=> [[AIPINJ - Upgrade Meetings]] | |
− | = | + | : Schedule Status => [[media:210125_AIPINJ_Schedule.pdf]] |
− | |||
− | : [[Phase 1 - HCO & Commissioning]] | ||
− | : [[AIPINJ - Upgrade Meetings]] | ||
− | : [ | ||
== Major Phase 1 Beamline Components == | == Major Phase 1 Beamline Components == | ||
Line 17: | Line 13: | ||
:[[DR dipole (15 deg)]] - New 15 deg air core bend dipole replaces pre-existing DS dipole | :[[DR dipole (15 deg)]] - New 15 deg air core bend dipole replaces pre-existing DS dipole | ||
:[[FX beamline and FY chopper solenoids]] - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID | :[[FX beamline and FY chopper solenoids]] - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID | ||
+ | :[[FG spin solenoids]] | ||
:[[PSS Kicker (upgraded for 200 kV upgrade)]] - New PSS kicker of reliable design to operate at 200 kV with shorter throw | :[[PSS Kicker (upgraded for 200 kV upgrade)]] - New PSS kicker of reliable design to operate at 200 kV with shorter throw | ||
:[[WF Wien Filters (200 kV upgrade)]] - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons | :[[WF Wien Filters (200 kV upgrade)]] - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons | ||
Line 30: | Line 27: | ||
==ATLIS Tasks== | ==ATLIS Tasks== | ||
+ | '''Open, complete, re-scheduled statuses updated 3/15/21''' | ||
;AIPINJ | ;AIPINJ | ||
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22151 AIPINJ: temporary 5D beam line removal] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22161 Removal/Er-installation of Part of 5D line in Inj.] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21911 Gun high voltage conditioning] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21370 Injector Wien Filter - system upgrade (2020 SAD)] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21164 Mat'l Handling and Installation for Phase I of Inj. Upgrade] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19517 Penetration Drops] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20270 Remove and re-install BPM's Gun to chopper] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21332 Removal of PSS kicker magnet injector segment] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20395 Pedestal Location Surveys] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20268 Remove and calibrate current monitoring electronics] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20404 Install Chopper SSA's] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/17932 Harp work] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20268 Remove and calibrate current monitoring electronics] |
− | * [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1273 Testing Wien HV Controls at UITF] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/17932 Harp work] |
− | * [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/20275 Perform Installation work for newly added Injector bpm during 2020 SAD] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1273 Testing Wien HV Controls at UITF] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/20275 Perform Installation work for newly added Injector bpm during 2020 SAD] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id= | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21431 Install and Commission Wien filter Power Supplies] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21570 Install PSS jumpers for laser work at the Injector] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21198 Survey support for Injector Upgrade] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21922 Relocate Recepacles Downstairs in Injector Bldg.53] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22071 DC Power Support for Injector Upgrade] |
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22201 STAC5 A1 Aperture Epics Controls] | ||
+ | |||
+ | |||
+ | * '''Complete''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20410 Chopper SSA LCW] | ||
+ | * '''Complete''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21490 IOCSE11 & IOCINSE4 BPM Controls Update] | ||
+ | * '''Complete''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21570 Install PSS jumpers for laser work at the Injector] | ||
+ | * '''Complete''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21922 Relocate Recepacles Downstairs in Injector Bldg.53] | ||
+ | * '''Complete''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21211 Install Lifting Plates in Ijn. Ceiling to Support 1/4 CM Swap] | ||
+ | |||
;CIS SAD Tasks | ;CIS SAD Tasks | ||
− | * [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19463 New Gun2 loading chamber] | + | * '''Open''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19463 New Gun2 loading chamber] |
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21920 CEBAF Lead Bricks : Collect, Sort, Clean, Paint, Store] | ||
* Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard | * Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard | ||
− | * [https://logbooks.jlab.org/entry/3844689 Fix IHWP readback during SAD] | + | * '''Open''' No ATLis [https://logbooks.jlab.org/entry/3844689 Fix IHWP readback during SAD] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/ | + | |
+ | |||
+ | * '''Complete''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=20383 Injector Macropulse/Tune Mode Generator Modification] | ||
+ | |||
;Injector Related SAD Tasks | ;Injector Related SAD Tasks | ||
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22130 LLRF Diagnostics and Repairs in the Linacs and Injector] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22100 April 2021 10 Amp System PM Maintenance] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22020 Annual Crane Inspections Site wide May 17- May 27 2021] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/ | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21316 VME FSD Master Card Commisioning] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21330 PSS Injector Interface Chassis removal] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21288 429 mHz Amp & Power supply being pulled for repair] |
− | * [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21542 PSS CAMAC Relay cards replacement with VME versions for Injector and BSY] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20271 2020 SAD Injector / North Linac 30 Hz System checks] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20415 I&C Injector Camac to Vme and camera upgrade] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21353 Install Ion Pump HV cables and mount Junction boxes on cable trays NL and INJ] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/17247 I&C Upgrade harps to PC104] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21330 PSS Injector Interface Chassis removal] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21331 I&C Upgrade existing ItoV System with ItoV VME cards] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21145 PSS Injector Segment PLC Upgrade] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/18471 I&C Accelerator network re-survey] | + | * '''Open''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21542 PSS CAMAC Relay cards replacement with VME versions for Injector and BSY] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21334 FAC Tunnel Fire Alarm and Suppression Replacement] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20415 I&C Injector Camac to Vme and camera upgrade] |
− | * [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21242 Apply labels to I&C components during 2020 SAD] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/17247 I&C Upgrade harps to PC104] |
− | * | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21331 I&C Upgrade existing ItoV System with ItoV VME cards] |
− | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/18471 I&C Accelerator network re-survey] | |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20644 UHV Power Supply Replacement (ISB)] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21334 FAC Tunnel Fire Alarm and Suppression Replacement] |
− | * | + | * '''Open''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21242 Apply labels to I&C components during 2020 SAD] |
− | + | * '''Open''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21020 Neutron Detector System Installation (SAD 2020)] | |
− | * [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21421 SAD 2020: P.M. of 24V Vacuum Power Supply Chassis] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20644 UHV Power Supply Replacement (ISB)] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21680 VME crate upgrade to IOCIN3] | + | * '''Open''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21373 Trim Utility Chassis Upgrade - All CEBAF Trim Racks] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21653 Remove old Sonitrol system hardware from NA and SA] | + | * '''Open''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21421 SAD 2020: P.M. of 24V Vacuum Power Supply Chassis] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21696 Shutdown of Panel I-BT in the Injector] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21680 VME crate upgrade to IOCIN3] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21881 Insertable CAMAC to VME EPICS Controls upgrade Injector (iocin1->iocin1b) ] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21653 Remove old Sonitrol system hardware from NA and SA] |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21850 Software Controls PSS Injector and North Linac changes on iocsoftsafe2] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21696 Shutdown of Panel I-BT in the Injector] |
− | * | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21881 Insertable CAMAC to VME EPICS Controls upgrade Injector (iocin1->iocin1b) ] |
− | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21850 Software Controls PSS Injector and North Linac changes on iocsoftsafe2] | |
− | * [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=20311 2020 SAD and Beyond CAMAC / VME PM maintenance and repairs] | + | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21912 Perform Basic PM of 45 MeV spectrometer Power Supply] |
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=20311 2020 SAD and Beyond CAMAC / VME PM maintenance and repairs] | ||
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21981 iocin1 - VME crate replacement] | ||
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21379 Study - Site Ground Loop] | ||
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21103 Change transformer tap settings - oil filled transformers] | ||
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21991 Injector Survey Monuments install] | ||
+ | * '''Open''' [http://devweb.acc.jlab.org/CSUEApps/atlis/task/20972 Remove Old 45MeV Dump and re-Install at End of SAD] | ||
+ | |||
+ | |||
+ | * '''Complete''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21882 B53 (INJ SB) Panelboard PM] | ||
+ | |||
+ | |||
+ | * '''Rescheduled''' [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21376 Injector (prebuncher, buncher and choppers)- LLRF systems upgrade to 3.0 version] |
Revision as of 18:06, 7 April 2021
Quick Phase 1 Links
- ATLIS => Phase 1 ATLIS
- 8:30 Tools => CIS Phase 1 work plans
- HCO => Phase 1 - HCO & Commissioning
- Meetings=> AIPINJ - Upgrade Meetings
- Schedule Status => media:210125_AIPINJ_Schedule.pdf
Major Phase 1 Beamline Components
- 200 kV gun - Cathode, anode and high voltage system
- 200 kV NEG Coated BPM's - New BPM's on beam pipe, NEG coated and absolutely mapped
- Y-chamber Laser Window - Evaluating the best window to minimize birefringence under stress
- DR dipole (15 deg) - New 15 deg air core bend dipole replaces pre-existing DS dipole
- FX beamline and FY chopper solenoids - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
- FG spin solenoids
- PSS Kicker (upgraded for 200 kV upgrade) - New PSS kicker of reliable design to operate at 200 kV with shorter throw
- WF Wien Filters (200 kV upgrade) - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons
- QW Wien quadrupoles (200 kV upgrade) - New quads designed for 200 keV energy, w/ improved magnetic field quality
- Chopping System (200 kV upgrade) - Choppers get higher power amplifiers, maybe a new chopping chamber
- Pre-buncher cavity (200 kV upgrade) - Existing stainless steel pre-buncher replaced by copper cavity for higher power.
- NEG coated 2.5 inch OD BPM's - Replacing (2) existing with (3) new BPM's, provide (x,x',y,y') from gun, help tuning
- HD steering coils - New steering coils for the A1/A2 aperture cubes, improved design and for 200 keV energy
- A1/A2 Aperture Steering Cubes - Reinvented A1/A2 apertures define beam size and PSS kicker destination, include upgraded HD steering coils
- Injector upgrade vacuum improvements - Improvements in the vacuum design, use of getter and ion pumps
- Beamline viewers
- LLRF 3.0 Phase 1
ATLIS Tasks
Open, complete, re-scheduled statuses updated 3/15/21
- AIPINJ
- Open AIPINJ: temporary 5D beam line removal
- Open Removal/Er-installation of Part of 5D line in Inj.
- Open Gun high voltage conditioning
- Open Injector Wien Filter - system upgrade (2020 SAD)
- Open Mat'l Handling and Installation for Phase I of Inj. Upgrade
- Open Penetration Drops
- Open Remove and re-install BPM's Gun to chopper
- Open Removal of PSS kicker magnet injector segment
- Open Pedestal Location Surveys
- Open Install Chopper SSA's
- Open Remove and calibrate current monitoring electronics
- Open Harp work
- Open Testing Wien HV Controls at UITF
- Open Perform Installation work for newly added Injector bpm during 2020 SAD
- Open Install and Commission Wien filter Power Supplies
- Open Survey support for Injector Upgrade
- Open DC Power Support for Injector Upgrade
- Open STAC5 A1 Aperture Epics Controls
- Complete Chopper SSA LCW
- Complete IOCSE11 & IOCINSE4 BPM Controls Update
- Complete Install PSS jumpers for laser work at the Injector
- Complete Relocate Recepacles Downstairs in Injector Bldg.53
- Complete Install Lifting Plates in Ijn. Ceiling to Support 1/4 CM Swap
- CIS SAD Tasks
- Open New Gun2 loading chamber
- Open CEBAF Lead Bricks : Collect, Sort, Clean, Paint, Store
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard
- Open No ATLis Fix IHWP readback during SAD
- Injector Related SAD Tasks
- Open LLRF Diagnostics and Repairs in the Linacs and Injector
- Open April 2021 10 Amp System PM Maintenance
- Open Annual Crane Inspections Site wide May 17- May 27 2021
- Open VME FSD Master Card Commisioning
- Open 429 mHz Amp & Power supply being pulled for repair
- Open 2020 SAD Injector / North Linac 30 Hz System checks
- Open Install Ion Pump HV cables and mount Junction boxes on cable trays NL and INJ
- Open PSS Injector Interface Chassis removal
- Open PSS Injector Segment PLC Upgrade
- Open PSS CAMAC Relay cards replacement with VME versions for Injector and BSY
- Open I&C Injector Camac to Vme and camera upgrade
- Open I&C Upgrade harps to PC104
- Open I&C Upgrade existing ItoV System with ItoV VME cards
- Open I&C Accelerator network re-survey
- Open FAC Tunnel Fire Alarm and Suppression Replacement
- Open Apply labels to I&C components during 2020 SAD
- Open Neutron Detector System Installation (SAD 2020)
- Open UHV Power Supply Replacement (ISB)
- Open Trim Utility Chassis Upgrade - All CEBAF Trim Racks
- Open SAD 2020: P.M. of 24V Vacuum Power Supply Chassis
- Open VME crate upgrade to IOCIN3
- Open Remove old Sonitrol system hardware from NA and SA
- Open Shutdown of Panel I-BT in the Injector
- Open Insertable CAMAC to VME EPICS Controls upgrade Injector (iocin1->iocin1b)
- Open Software Controls PSS Injector and North Linac changes on iocsoftsafe2
- Open Perform Basic PM of 45 MeV spectrometer Power Supply
- Open 2020 SAD and Beyond CAMAC / VME PM maintenance and repairs
- Open iocin1 - VME crate replacement
- Open Study - Site Ground Loop
- Open Change transformer tap settings - oil filled transformers
- Open Injector Survey Monuments install
- Open Remove Old 45MeV Dump and re-Install at End of SAD
- Complete B53 (INJ SB) Panelboard PM