Difference between revisions of "NPS Assembly"
Jump to navigation
Jump to search
Line 56: | Line 56: | ||
:::* crystal stacking | :::* crystal stacking | ||
:::* PMT block assembly | :::* PMT block assembly | ||
− | :::* cabling and installation of the big PCBs | + | :::* cabling and installation of the big PCBs [https://wiki.jlab.org/cuawiki/images/2/23/NPS-assembly-with-PCBs.png Pic1], [https://wiki.jlab.org/cuawiki/images/d/d3/NPS-assembly-with-PCBs-from-front.png Pic2], [https://wiki.jlab.org/cuawiki/images/a/a3/NPS-assembly-with-PCBs-PMT-maintenance.png Pic3], [https://wiki.jlab.org/cuawiki/images/6/60/NPS-assembly-with-PCBs-side-closeup.png Pic4], [https://wiki.jlab.org/cuawiki/images/2/27/NPS-assembly-with-PCBs-side-closeup-2.png Pic5] |
:::* preparation for detector checkout | :::* preparation for detector checkout | ||
:::* detector checkout | :::* detector checkout |
Revision as of 14:16, 7 February 2023
Task List 2022
- Link to the Google Doc
Resource List
Pre-assembly - COMPLETE (5/27/2022)
- On site personnel: AANL (Hamlet Mkrtchyan, Vardan Tadevosyan), CUA (Vladimir Berdnikov, Josh Crafts, Petr Stepanov), MSU (Abishek Karki), UIC (ZHeng Huang); onsite contacts: Vladimir, Brad
- Reflector pre-shaping procedure and material
- Crystal Wrapping Procedure Link
- Crystal Wrapping Documentation
Cabling - COMPLETE (11/18/2022)
- Onsite contacts: Yeran, Brad
- Partisipants
- AANL (A.Alikhanyan National Science Laboratory)
- Mkrtchyan Hamlet
- Voskanyan Hakob
- Tadevosyan Vardan
- Mkrtchyan Arthur
- CUA (Catholic University of America)
- Ghandilyan Yeranuhi
- MSU (Mississippi State Universtiy)
- Abishek Karki
- OU (Ohio University)
- Pramita Tiwari
- GU (University of Glasgow)
- Oliver Jevons
- Gary Penman
- Bundling
- putting 12 cables on the ground one by one on
- tying with zip ties in each 3m
- making a bundle
- Total number of the cables 2160, total number of the boxes with cables - 180, total number of bundles - 180
Assembly
- Crystal stacking - COMPLETE (10 June 2022)
- onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2); onsite contacts: Carlos, Vladimir, Brad
- All crystals are stacked and 4 full columns of PMTs and electronics are cabled - assembled NPS picture
- Preparation for detector checkout - planned for July/August
- onsite personnel: AANL (2), CUA (1-2), OU (2-3); onsite contacts: Brad, Julie/Paul, Carlos
- In order to perform the detector tests, there is work to be done outside the calorimeter box:
- HV cables, signal cables and LV cables need to be put in place and hooked to the DAQ, which needs to be setup.
- Power supplies (HV, LV) need to be setup.
- Same for slow controls (for HV and LED), etc.
- Detector Checkout - planned for August
- onsite personnel: OU (1-2), AANL (2), CUA (1-2), U. Glasgow (3); onsite contacts: Brad, David H.
- Detector checkout plans and task lists
- Crystal+PMT+Cable module map as viewed from the back
Mechanical
- NPS Deck Pictures (April 2022)
- NPS Deck Pictures (March 2022)
DAQ/Electronics/Analyzer
- Link to DAQ/Electronics/Analyzer activities; contact David Hamilton for details.
- GitHub link (contact Brad, Carlos Y., or Steve W. for access)
Magnet
Crystals
- Overview of crystal properties
- spreadsheet from CRYTUR (January 2022) (dimensions, transmittance, light yield, radiation hardness)