Difference between revisions of "NPS Assembly"
Jump to navigation
Jump to search
Line 9: | Line 9: | ||
=== Pre-assembly - COMPLETE (5/27/2022) === | === Pre-assembly - COMPLETE (5/27/2022) === | ||
− | * On site personnel: AANL ( | + | * On site personnel: AANL (Hamlet Mkrtchyan, Vardan Tadevosyan), CUA (Vladimir Berdnikov, Josh Crafts, Petr Stepanov), MSU (Abishek), UIC (ZHeng Huang); onsite contacts: Vladimir, Brad |
* Reflector pre-shaping procedure and material | * Reflector pre-shaping procedure and material |
Revision as of 08:27, 1 December 2022
Task List 2022
- Link to the Google Doc
Resource List
Pre-assembly - COMPLETE (5/27/2022)
- On site personnel: AANL (Hamlet Mkrtchyan, Vardan Tadevosyan), CUA (Vladimir Berdnikov, Josh Crafts, Petr Stepanov), MSU (Abishek), UIC (ZHeng Huang); onsite contacts: Vladimir, Brad
- Reflector pre-shaping procedure and material
- Crystal Wrapping Procedure Link
- Crystal Wrapping Documentation
Cabling - COMPLETE (11/18/2022)
- Onsite contacts: Yeran, Brad
- Partisipants
- AANL (A.Alikhanyan National Science Laboratory)
- Mkrtchyan Hamlet
- Voskanyan Hakob
- Tadevosyan Vardan
- Mkrtchyan Arthur
- CUA (Catholic University of America)
- Ghandilyan Yeranuhi
- MSU (Mississippi State Universtiy)
- Abishek Karki
- OU (Ohio University)
- Pramita Tiwari
- GU (University of Glasgow)
- Oliver Jevons
- Gary Penman
- Bundling
- putting 12 cables on the ground one by one on
- tying with zip ties in each 3m
- making a bundle
- Total number of the cables 2160, total number of the boxes with cables - 180, total number of bundles - 180
Assembly
- Multiple phases:
- crystal stacking
- PMT block assembly
- cabling and installation of the big PCBs
- preparation for detector checkout
- detector checkout
- Crystal stacking - COMPLETE (10 June 2022)
- onsite personnel: IJCLab-Orsay (6), AANL (2), CUA (2-3), OU (1-2); onsite contacts: Carlos, Vladimir, Brad
- All crystals are stacked and 4 full columns of PMTs and electronics are cabled - assembled NPS picture
- Preparation for detector checkout - planned for July/August
- onsite personnel: AANL (2), CUA (1-2), OU (2-3); onsite contacts: Brad, Julie/Paul, Carlos
- In order to perform the detector tests, there is work to be done outside the calorimeter box:
- HV cables, signal cables and LV cables need to be put in place and hooked to the DAQ, which needs to be setup.
- Power supplies (HV, LV) need to be setup.
- Same for slow controls (for HV and LED), etc.
- Detector Checkout - planned for August
- onsite personnel: OU (1-2), AANL (2), CUA (1-2), U. Glasgow (3); onsite contacts: Brad, David H.
- Detector checkout plans and task lists
Mechanical
- NPS Deck Pictures (April 2022)
- NPS Deck Pictures (March 2022)
DAQ/Electronics/Analyzer
- Link to DAQ/Electronics/Analyzer activities; contact David Hamilton for details.
- GitHub link (contact Brad, Carlos Y., or Steve W. for access)
Magnet
Crystals
- Overview of crystal properties
- spreadsheet from CRYTUR (January 2022) (dimensions, transmittance, light yield, radiation hardness)