Phase 1
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Quick Phase 1 Links
- ATLIS => Phase 1 ATLIS
- 8:30 Tools => CIS Phase 1 work plans
- HCO => Phase 1 - HCO & Commissioning
- Meetings=> AIPINJ - Upgrade Meetings
- Schedule Status => media:210125_AIPINJ_Schedule.pdf
Major Phase 1 Beamline Components
- 200 kV gun - Cathode, anode and high voltage system
- 200 kV NEG Coated BPM's - New BPM's on beam pipe, NEG coated and absolutely mapped
- Y-chamber Laser Window - Evaluating the best window to minimize birefringence under stress
- DR dipole (15 deg) - New 15 deg air core bend dipole replaces pre-existing DS dipole
- Solenoid Details
- Agreed solenoid field direction convention => https://logbooks.jlab.org/entry/3256163
- Phase 1 wiring diagram info => media:210419_Magnet_Wiring_v6.docx
- FX beamline and FY chopper solenoids - New double-coil sw/cw capable solenoids with 38 mm (FX) and 46 mm (FY) ID
- FG spin solenoids
- PSS Kicker (upgraded for 200 kV upgrade) - New PSS kicker of reliable design to operate at 200 kV with shorter throw
- WF Wien Filters (200 kV upgrade) - Upgraded Wien filters with 20 A magnetic coils and >18 kV electrodes to rotate spin of 200 keV electrons
- QW Wien quadrupoles (200 kV upgrade) - New quads designed for 200 keV energy, w/ improved magnetic field quality
- Chopping System (200 kV upgrade) - Choppers get higher power amplifiers, maybe a new chopping chamber
- Pre-buncher cavity (200 kV upgrade) - Existing stainless steel pre-buncher replaced by copper cavity for higher power.
- NEG coated 2.5 inch OD BPM's - Replacing (2) existing with (3) new BPM's, provide (x,x',y,y') from gun, help tuning
- HD steering coils - New steering coils for the A1/A2 aperture cubes, improved design and for 200 keV energy
- A1/A2 Aperture Steering Cubes - Reinvented A1/A2 apertures define beam size and PSS kicker destination, include upgraded HD steering coils
- Injector upgrade vacuum improvements - Improvements in the vacuum design, use of getter and ion pumps
- Beamline viewers
- LLRF 3.0 Phase 1
ATLIS Tasks
Open, complete, re-scheduled statuses updated 3/15/21
- AIPINJ
- Open AIPINJ: temporary 5D beam line removal
- Open Removal/Er-installation of Part of 5D line in Inj.
- Open Gun high voltage conditioning
- Open Injector Wien Filter - system upgrade (2020 SAD)
- Open Mat'l Handling and Installation for Phase I of Inj. Upgrade
- Open Penetration Drops
- Open Remove and re-install BPM's Gun to chopper
- Open Removal of PSS kicker magnet injector segment
- Open Pedestal Location Surveys
- Open Install Chopper SSA's
- Open Remove and calibrate current monitoring electronics
- Open Harp work
- Open Testing Wien HV Controls at UITF
- Open Perform Installation work for newly added Injector bpm during 2020 SAD
- Open Install and Commission Wien filter Power Supplies
- Open Survey support for Injector Upgrade
- Open DC Power Support for Injector Upgrade
- Open STAC5 A1 Aperture Epics Controls
- Complete Chopper SSA LCW
- Complete IOCSE11 & IOCINSE4 BPM Controls Update
- Complete Install PSS jumpers for laser work at the Injector
- Complete Relocate Recepacles Downstairs in Injector Bldg.53
- Complete Install Lifting Plates in Ijn. Ceiling to Support 1/4 CM Swap
- CIS SAD Tasks
- Open New Gun2 loading chamber
- Open CEBAF Lead Bricks : Collect, Sort, Clean, Paint, Store
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard
- Open No ATLis Fix IHWP readback during SAD
- Injector Related SAD Tasks
- Open LLRF Diagnostics and Repairs in the Linacs and Injector
- Open April 2021 10 Amp System PM Maintenance
- Open Annual Crane Inspections Site wide May 17- May 27 2021
- Open VME FSD Master Card Commisioning
- Open 429 mHz Amp & Power supply being pulled for repair
- Open 2020 SAD Injector / North Linac 30 Hz System checks
- Open Install Ion Pump HV cables and mount Junction boxes on cable trays NL and INJ
- Open PSS Injector Interface Chassis removal
- Open PSS Injector Segment PLC Upgrade
- Open PSS CAMAC Relay cards replacement with VME versions for Injector and BSY
- Open I&C Injector Camac to Vme and camera upgrade
- Open I&C Upgrade harps to PC104
- Open I&C Upgrade existing ItoV System with ItoV VME cards
- Open I&C Accelerator network re-survey
- Open FAC Tunnel Fire Alarm and Suppression Replacement
- Open Apply labels to I&C components during 2020 SAD
- Open Neutron Detector System Installation (SAD 2020)
- Open UHV Power Supply Replacement (ISB)
- Open Trim Utility Chassis Upgrade - All CEBAF Trim Racks
- Open SAD 2020: P.M. of 24V Vacuum Power Supply Chassis
- Open VME crate upgrade to IOCIN3
- Open Remove old Sonitrol system hardware from NA and SA
- Open Shutdown of Panel I-BT in the Injector
- Open Insertable CAMAC to VME EPICS Controls upgrade Injector (iocin1->iocin1b)
- Open Software Controls PSS Injector and North Linac changes on iocsoftsafe2
- Open Perform Basic PM of 45 MeV spectrometer Power Supply
- Open 2020 SAD and Beyond CAMAC / VME PM maintenance and repairs
- Open iocin1 - VME crate replacement
- Open Study - Site Ground Loop
- Open Change transformer tap settings - oil filled transformers
- Open Injector Survey Monuments install
- Open Remove Old 45MeV Dump and re-Install at End of SAD
- Complete B53 (INJ SB) Panelboard PM