=== Owl shift ===
 
=== Owl shift ===
# Shift summary by the shift expert:
+
# Shift summary by the shift expert: https://logbooks.jlab.org/entry/3840690
# Issues:  
+
# Issues: High rates on upstream halo counters; only remedy proposed by MCC is raising the FSD threshold to 2600.
# Recorded data:  
+
# Recorded data: 32.2 M events
  
 
=== Day shift ===
 
=== Day shift ===
# Shift summary by the shift expert:  
+
# Shift summary by the shift expert: https://logbooks.jlab.org/entry/3840902
# Issues:  
+
# Issues: No beam - accelerator trying to tune orbits, then 1L19 drops out again. Attempt to tune beam on tagger failed (high upstream counter rates even with beam to Hall off).
# Recorded data:  
+
# Recorded data: 0
  
 
=== Swing shift ===
 
=== Swing shift ===
 
# Shift summary by the shift expert:  
 
# Shift summary by the shift expert:  
# Issues:  
+
# Issues: Still no beam. MCAT04 magnet may have been energized to low (would explain scraping): https://logbooks.jlab.org/entry/3841133.
 
# Recorded data:
 
# Recorded data:
  

Revision as of 18:27, 4 September 2020

Back to Run Group F | Daily Run Group F Coordination Meetings


2020

March
19, 20, 21, 22, 23, 24
July
31
August
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31
September
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21

RC:

Summary of Sep. 4th

Owl shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3840690
  2. Issues: High rates on upstream halo counters; only remedy proposed by MCC is raising the FSD threshold to 2600.
  3. Recorded data: 32.2 M events

Day shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3840902
  2. Issues: No beam - accelerator trying to tune orbits, then 1L19 drops out again. Attempt to tune beam on tagger failed (high upstream counter rates even with beam to Hall off).
  3. Recorded data: 0

Swing shift

  1. Shift summary by the shift expert:
  2. Issues: Still no beam. MCAT04 magnet may have been energized to low (would explain scraping): https://logbooks.jlab.org/entry/3841133.
  3. Recorded data:

Whole day summary

  1. Total recorded data today:
  2. Part-II total accumulated data on D2:
  3. Concerns:


Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/

Recorded data numbers

Number of events recorded