Difference between revisions of "RC Meeting: September 8th, 2020"

From clas12-run
Jump to navigation Jump to search
(Created page with "Back to Run Group F | Daily Run Group F Coordination Meetings ==2020== {| class="wikitable" border="1" style="text-align:center;border-collapse:collapse...")
 
 
Line 28: Line 28:
  
 
=== Owl shift ===
 
=== Owl shift ===
# Shift summary by the shift expert:
+
# Shift summary by the shift expert: https://logbooks.jlab.org/entry/3843547
# Issues:  
+
# Issues: Several accelerator issues
# Recorded data:  
+
# Recorded data: 7.7 M events on D2
  
 
=== Day shift ===
 
=== Day shift ===
# Shift summary by the shift expert:  
+
# Shift summary by the shift expert: https://logbooks.jlab.org/entry/3843770
# Issues:  
+
# Issues: Beam off at beginning, then high beam counter rates, then DAQ crash (SVT3 = MVT3 ROC). Went into controlled access for beamline repair at 11:30
# Recorded data:  
+
# Recorded data: 3.9 M events on D2
  
 
=== Swing shift ===
 
=== Swing shift ===
# Shift summary by the shift expert:  
+
# Shift summary by the shift expert: https://logbooks.jlab.org/entry/3844034
# Issues:  
+
# Issues: Beamline exit window repair unsuccessful. Down until new exit window can be prepared. Shift ended early.
# Recorded data:
+
# Recorded data: Zilch
  
 
=== Whole day summary ===
 
=== Whole day summary ===
# Total recorded data today:  
+
# Total recorded data today: 11.7 M events - please fire the RC!
# Part-II total accumulated data on D2:  
+
# Part-II total accumulated data on D2: only a rounding error from yesterday (1.66 B events)
#Concerns:  
+
#Concerns: Beam line exit window repair will likely take until at least noon tomorrow. Then we will have to put everything back into working order. Owl shift is cancelled.
  
  

Latest revision as of 17:24, 8 September 2020

Back to Run Group F | Daily Run Group F Coordination Meetings


2020

March
19, 20, 21, 22, 23, 24
July
31
August
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31
September
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21

RC:

Summary of Sep. 8th

Owl shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3843547
  2. Issues: Several accelerator issues
  3. Recorded data: 7.7 M events on D2

Day shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3843770
  2. Issues: Beam off at beginning, then high beam counter rates, then DAQ crash (SVT3 = MVT3 ROC). Went into controlled access for beamline repair at 11:30
  3. Recorded data: 3.9 M events on D2

Swing shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3844034
  2. Issues: Beamline exit window repair unsuccessful. Down until new exit window can be prepared. Shift ended early.
  3. Recorded data: Zilch

Whole day summary

  1. Total recorded data today: 11.7 M events - please fire the RC!
  2. Part-II total accumulated data on D2: only a rounding error from yesterday (1.66 B events)
  3. Concerns: Beam line exit window repair will likely take until at least noon tomorrow. Then we will have to put everything back into working order. Owl shift is cancelled.


Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/

Recorded data numbers

Number of events recorded