RC Meeting: September 11th, 2020

From clas12-run
Revision as of 10:06, 11 September 2020 by Hattawy (talk | contribs) (→‎Day shift)
Jump to navigation Jump to search

Back to Run Group F | Daily Run Group F Coordination Meetings


2020

March
19, 20, 21, 22, 23, 24
July
31
August
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31
September
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21

RC:

Summary of Sep. 11th

Owl shift

  1. Shift summary by the shift expert:https://logbooks.jlab.org/entry/3845749
  2. Issues: started production with 200nA->240nA. the beam went down at 2:20 AM (ion pump is dead in the south linac) shifted ended before beam back.
  3. Recorded data: 8M on D2

Day shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3845976
  2. Issues: beam down at 9:40 AM - ... (1L20 tripped due to low liquid level, 5th Pass H. Separator:cabling is heating up, three dipoles tripped off(BSY1C, 2C, 3C))
  3. Recorded data: 3M on D2 (240 nA)

Swing shift

  1. Shift summary by the shift expert:
  2. Issues:
  3. Recorded data:

Whole day summary

  1. Total recorded data today:
  2. Part-II total accumulated data on D2:
  3. Concerns:


Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/

Recorded data numbers

Number of events recorded