RC Meeting: September 13th, 2020
Back to Run Group F | Daily Run Group F Coordination Meetings
2020
March |
---|
19, 20, 21, 22, 23, 24 |
July |
31 |
August |
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31 |
September |
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21 |
RC: M. Hattawy
Summary of Sep. 13th
Owl shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3846944
- Issues: beam down 7 hours some cavities in the injector are getting warm and losing their gradient
- Recorded data: 2M on D2
Day shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3847058
- Issues: 8 hours beam down on 1L17 not ramping HV.
- Recorded data: none
Swing shift
- Shift summary by the shift expert:
- Issues:
- Recorded data:
Whole day summary
- Total recorded data today:
- Part-II total accumulated data on D2:
- Concerns:
Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/