Summary of Aug. 24th

Owl shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3833031
  2. Issues: Magnet trouble in arc
  3. Recorded data: 20.5 M events D2 production

Day shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3833165
  2. Issues: DAQ crashes, increasing data rates, first sign of upstream halo counters also increasing
  3. Recorded data: 5 M events on empty (D2) target, 25 M events production on D2

Swing shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3833407
  2. Issues: New hot channel in RTPC
  3. Recorded data:

Whole day summary

  1. Total recorded data today:
  2. Part-II total accumulated data on D2:
  3. Concerns:


Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/

Recorded data numbers

Number of events recorded